a. Determine the expected time (t,) for each activity. 5. Identify the critical path(s) c. What is the shortest time to complete the entire project?
Q: A2 A4 A5 A3 Task Duration (days) 3 A1 3 A2 A3 1 A4 A5 days What is the late finish time for activity…
A: Using the Forward Path Early Start of the activity = Early Finish of predecessor activity Early…
Q: ACTIVITY PREC. ACT. TIME ESTIMATES (days) to 2 6. A. 2. D. 2 B. 7 C, D G. 2. r.G 2. ) Construct a…
A: As per the guidelines, the first 3 subparts are solved. Expected time = to+4×tm+tp6 Using the…
Q: 1- Data for small project are given, determine the following 1- ES for Activity C. E. G. J 2- E.F…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: a. Draw a project network. b. What is the critical path? c. What is the normal project cost? d.…
A: Find the Slope calculations below:
Q: SESSION 2– Individual exercise (for marks) Given the following activity precedence table, please…
A: The question is related to Critical Path Analysis. The details are given.
Q: Picture attached below
A: ACTIVITY DURATION ES EF LS LF SLACK CRITICAL A 3 0 3 0 3 3 - 3 = 0…
Q: Recently, you were assigned to manage a project to remodelthe seminar room for your company. You…
A: Given data is
Q: (1) Find the Early Start / Early Finish Time of Each Activity (2) Find the Late Start / Late Finish…
A:
Q: Draw the project PDM. b. Determine the critical path. c. Calculate the total slack time. а.
A: In this question, I would first determine the expected activity time for each activity, based on the…
Q: Q1: Draw the allocation of resources chart on the earliest and latest start time for the project…
A: In given network diagram critical path will pass the activities B−E−G−K duration of the…
Q: a) Create an activity network diagram that shows the sequential logic the project tasks. b) Identify…
A: The critical path method (CPM) is a method for determining schedule flexibility and identifying…
Q: Consider the following data for a project to install a new server at the Northland Pines High…
A: a.
Q: 1. Construct the activity-on-node network. 2. Identify the critical path. 3. Compute the duration of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Given the activities of a project, their tim redecessors shown below: 1. Draw the Gannt chart for…
A: Given: Activities Activity Times, months Immediate predecessors Maximum slack moths A 2 - B…
Q: d. How much slack is in Activity C? What does this mean? e. How much slack is in Activity E?
A: The critical task is the task that performs the operations on the critical path of the project that…
Q: Ql: For activities shown in table below, find the new time of project after updating, if the project…
A:
Q: For the project data shown in the table below. Find The expected time to complete 77 % of the…
A: Given data: To find the expected time to complete 77% of the project M=2*O P=3*0 Activity…
Q: 1. Determine the amount of slack in each of a project's activities (presented below), and identify…
A: We’ll answer the first question since the exact one wasn’t specified. Please submit a new question…
Q: Consider the following data for a project to install a newserver at the Northland Pines High School:…
A: The critical path method, or critical path analysis, refers to an algorithm which is used for…
Q: 1. Determine the amount of slack in each of a project's activities (presented below), and identify…
A:
Q: Given the activities whose sequence is described by thefol lowing table, draw the appropriate…
A: Critical path refers to the stage sequences, that require maximum time for the project completion.
Q: a) What is the expected time to complete the project?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: 1. of all the paths through a network , the critical path has the a. Maximum actual time b.…
A: Project network is the graphical representation that shows the project activities as well as their…
Q: days. Carl's team should be able to complete the project in
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: Consider the Work Breakdown Structure of this project. Immediate Activity Duration (days)…
A: Project duration is the time that any project takes to fully complete and deliver the final product…
Q: The Scott Corey accounting firm is installing a new computer system. Several things must be done to…
A: The method of analyzing the set of activities related to the project of the company is known as the…
Q: i. Calculate the expected time for each activity ii. Draw a Gantt Chart from the same information…
A: As per Bartleby guidelines we can only solve first 3 sub par Below is the solution:-
Q: What’s the significance of identifying the critical path?
A: Since you have asked multiple questions, we will answer the first question for you. If you want a…
Q: The activities related to a project with their immediate predecessors are given as follows: Activity…
A: Given data is
Q: a.How would you explain Project? One time activity to solve a problem b. Describe what happens…
A: Note: - Since the exact question that has to be answered is not specified, we will answer only the…
Q: b) The activities on the critical path are c) The total project completion time for Rafay Ishfaq's…
A: THE ANSWER IS AS BELOW:
Q: a. Draw the network diagram b. What is the critical path? c How many dayswill it take to complete…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: How long will the following project take to complete? Task Predecessor Time (days) A None 100 B A 50…
A: In order to find how much time it would take for the project to finish we need to find the Critical…
Q: Please help me answer parts 3. and 4. of this question if not all of them. Thank you
A: Forward Pass:Early Start = Maximum (or Highest) EF value from immediate Predecessor(s)Early Finish =…
Q: Explain how to determine the slack for each activity in aproject. Why is it important for managers…
A: Slack in a project is referred to as the time margin or extent to which a particular activity stated…
Q: For the project data shown in the table below. Find The expected time to complete 77 % of the…
A: The formulas:
Q: Given the activities whose sequence is describedby the following table, draw the appropriate…
A: Draw the path
Q: Construct a Gantt Chart assuming each activity starts at the earliest time possible. Based on the…
A: Given data is
Q: Given the activities of a project, their time estimates, and their immediate predecessors shown…
A: Given information Activity Activity Time Immediate predecessors A 2 B 3 C 2 A D 4…
Q: 1. Determine the amount of slack in each of a proiect's activities (presented below), and identify…
A: Formula:
Q: Part 2: The activity list shown below represents the activities, the job logic and activities'…
A: The AOA network diagram is the graphical representation that represents the activities and their…
Q: 1. What is the expected (estimated) time for each activity? 2. Based on the calculation of estimated…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Activity Immediate Predecessor(s) Estimated Activity Duration (in days) NONE 2 B A 4 A B 5 E C,D 8.…
A: The network diagram based on the given information is as follows:
Q: Which of the following activities is NOT considered a project? A. Developing a new software program…
A: Note: Since you have posted multiple independent questions in the same request, we will solve the…
Q: a. Construct the project network b. Determine the critical path c. Find the completion time of the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: 1. Define what a PERT diagram is relative to project planning, and explain the importance of a PERT…
A: Project planning is the concept of project management in which scheduling is used to develop…
Q: 1- The number of critical paths in the project is All options are incorrect O
A: One of the methods to find the longest duration that a project would take to complete is the…
number 2 PERT, pls answer a-c.
Step by step
Solved in 2 steps with 1 images
- 2. A company is faced with the following PERT network situ ation for a certain project (time in days): A 13 - 20 -17 2 -4 -6 Start 5-8 - 11 8 - 10 - 12 6-8-16 2- 12-22 9-12 -15 REQUIRED: a. Detemine the expected time (t,) for each activity. b. Identify the critical path(s) c. Whatis the shortest time to complete the entireproject?PERT-CPM 1. Consider a project involving the following activities and precedence relationship. The cost of each activity is listed. The following activity time estimates have been provided for a preparation involving an MIS project. a. Draw the AON and AOA Diagram. b. Perform a Program Evaluation and Review Technique (PERT) to determine the expected total duration of the project. [Note: Use the diagramming convention agreed in class and tabulate the results for each activity's ES, EF, LS, LF, slack time and indication if it's in the critical path Note: Expected (Ave Time) = (0ptimistic Time + 4*Most Likely Time + PessimisticTime) / 6 = ( OT + 4MLT + PT ) / 6 c. If the project exceeds 11 weeks, there is an additional miscellaneous costs around Php 30,000. Will the company opt to speed up the project? Activity Predecessors Optimistic Most Pessimistic Crash Normal Crashed Likely Time Cost Cost A 2 4 6. 2 11,000 6,000 3,000 7,000 4,000 13,000 9,000 4,000 5,000 3,000 3 17.000 В 1 3 5 1…The following activities are part of a project to be scheduled using CPM: TIME (WEEKS) 7 6 ACTIVITY IMMEDIATE PREDECESSOR A BCDEFG O A-C-D-E-G O A-B-E-G O A-C-D-F-G O A-B-D-F-G AACB A Number of weeks A b. What is the critical path? B, D D E, F 24346 c. How many weeks will it take to complete the project?
- Activity A B CDEFG 3. You have been appointed as the project leader of a project to be undertaken by your company. You have identified the following tasks and made the time estimates for each task as listed in the table below: с Preceding "from" activity A A A B,C C,D,E F Succeeding "to" activity B,C,D E E F F G Estimated duration work days) 3 5 3 10 8 14 7 a) Use the above table to construct a project network diagram. b) Determine the critical path for the project and its duration.1- The network below represents a project being analyzed by Critical Path Methods. Activity durations are A = 5, B =2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I= 10, and J= 6. E Start 10 a. What task must be on the critical path, regardless of activity durations? b. What is the duration of path A-B-E-H-J? c. What is the critical path of this network? d. What is the length of the critical path? e. What is slack time at activity H? f. What is the Late Finish of activity H? g. If activity C were delayed by two time units, what would happen to the project duration? 2- Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. 27°C Mostly s... ^ O )Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: a. the critical activities for the leadership training program development project are: _____ b. the project length for the leadership training program development project= __ days. c. Slack time for each of the activities is: Activity: Slack time: A ______ B ______ C ______ D ______ E ______ F ______ G ______
- The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS ACTIVITY A ABCDEFGH B-E-G-H b. What is the critical path? A-C-F-H OA-D-F-H A-D-G-H A A B C,D D, E F,G Project completion time a LLL23312 TIMES (DAYS) m •WNNW: 3 2 2 3 4 4 4 4 b 5 3 3 4 11 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. days 565Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 44 B Develop Client Prospectus ― 35 C Perform Design Analysis ― 46 D Program Back End A, B, C 43 E Program Front End A 27 F Project Consolidation D, E 36 (a) For the given project, fill in the nodes of the network diagram below. A E 44 27 Start B D F Finish Time 35 43 36 Time C 46 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…The following represents a project that should be scheduled using CPM: ACTIVITY A B C D E F G H IMMEDIATE PREDECESSORS A A B C, D D, E F,G b. What is the critical path? ⒸA-D-G-H OB-E-G-H ⒸA-C-F-H A-D-F-H Probability TIMES (DAYS) b Project completion time a 1 1 2 1 1 3 1 2 m 2 2 2 8 2 4 3 3 6 9 11 9 3 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. 11 11 11 X Answer is not complete. days d. What is the probability of completing this project within 19 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.
- The information in the table below is available for a large fund-raising project. Activity Activity Times (days) Activity Cost ($) Immediate Predecessor A 3 100 None B 4 150 None C 2 125 A D 5 175 B E 2 150 B F 4 200 C, D G 6 75 C H 2 50 C, D, E I 1 100 E J 4 75 D, E K 5 350 F, G L 3 150 G, H, I M 4 400 I, J N 4 175 K, M O 1 200 H, M P 5 150 N, L, O Draw the precedence network diagram. Perform the CPM (Critical Path Method) and give the complete activity schedule table, the project completion time, and the critical path. Plot on the same graph the total project costs per day, starting from day one to the completion date, assuming the earliest start times and then assuming the latest start times. What implications does the time differential have for cash flows and project scheduling? Show step by step solutionHumber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 33 B Develop Client Prospectus ― 21 C Perform Design Analysis ― 35 D Program Back End A, B, C 47 E Program Front End A 13 F Project Consolidation D, E 11 (a) For the given project, fill in the nodes of the network diagram below. A E 33 13 Start B D F Finish Time 21 47 11 Time C 35 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…1. Data for a simplified PERT network are given below: a. Set up a table and calculate Early Event Times (TE), Late Event Times (TL), Activity Free Slack (AFS), and Activity Total Slack (ATS). b. Determine the PERT "critical path(s)" and the mean and standard deviation for the project duration. c. Determine the probability of completing the project in 25 days or less. d. Determine that the project will take 27 days or more. e. Determine the probability of reaching event 35 in 20 days or less. Time Estimates (days) i АСТ b a m 10 A 1 3 5 15 B 2 5 10 20 C 4 7 10 25 E 8. 10 12 IP F 15 25 15 30 4 8 9. 20 35 G 5 7 14 25 35 L 7 10 16 30 35 d2 30 40 12 35 45 N 1 3 7 40 45 P 3 5 7