d. How much slack is in Activity C? What does this mean? e. How much slack is in Activity E?
Q: i. Discuss the concept of Critical Path in project scheduling? Outline how this is identified and if…
A: 1. Critical Path One of the most often used project planning strategies is the critical route…
Q: Prepare a schedule based on resources. There are only 3 resources available for each period.…
A: 1. Possible path Duration Maximum duration Critical path 1-2-7 = 2+6+2 = 10 No No 1-3-5-7 =…
Q: A project's activities must be completed in the sequence indicated below. Activity Duration…
A: A network diagram is a visual representation of a project which helps to identify the critical path…
Q: a. Which activity has the largest slack?
A: THE ANSWER IS AS BELOW:
Q: If an activity has a total duration of 8 days and the schedule is 50% complete, how many days until…
A:
Q: The "Early Finish" of activity "C" is * 15 9. 30 21 O O O O
A: Project management is the management in which different types of knowledge and skills are needed to…
Q: The following represents a project with known activity times. All times are in weeks. Activity…
A: Given that: Activity Immediate Predecessors Duration A - 4 B - 3 C A 2 D B 7 E C, D 4…
Q: Which of the following activities is not part of defining a project?a. The project triangleb. The…
A: An organization has numerous projects running at a time and numerous projects in the pipeline to be…
Q: 44. What activities make up the critical path? In crashing this project, which activity is the first…
A: Project crashing is the process of reducing the activity duration using additional cost through…
Q: Q1. HOW MUCH SLACK DOES EACH ACTIVITY HAS?
A: Slack time is the difference between the late finish and the early finish of the activities.
Q: (1) Find the Early Start / Early Finish Time of Each Activity (2) Find the Late Start / Late Finish…
A:
Q: 1. Jim's team has completed the WBS and WBS dictionary and the stakeholders have approved the…
A: The correct option is "d", which is "DECOMPOSITION". Decomposition would involve dividing the…
Q: d. How long the program is expected to finish? e. Determine the slack time for each activity using…
A: given,
Q: Q1:- The timetable for one of the projects was as in Table No. (1), answer the following: 1- Draw…
A: Below is the solution:-
Q: e) The activity variance along the critical path is|weeks. (Round your response to two decimal…
A: The critical path is the longest path taken by project activities to complete the project in project…
Q: Consider the AON graph of a project shown below. A4 Figure 19.17 A3 A6 (A8 (A7 A2 A1 A5 The activity…
A: in order to find the earliest competition time from the activity-on-node diagram above, we need to…
Q: A project manager has compiled a list of major activities that will be required to install a…
A: The Time estimate can be calculated using formula = (Optimistic+4*Most Likely+Pessimistic)/6 Std Dev…
Q: (f) What is the largest number of weeks allotted to finish the electrical wirings without delaying…
A: Below is the solution:-
Q: What are some reasons project scheduling is not done well?
A: Project is an activity or the set of interrelated tasks that was generated in order to meet the…
Q: Project Sand Mandala Carrie meticulousiy calculated the eariy and late start and finish times for…
A: Critical path is the longest path that takes the maximum time to complete all the tasks of the…
Q: В- using the table below, Activity Predecessor Duration A A A D E 1 В E,C F D,B 1- How many paths…
A: The project network diagram is the visual representation of project tasks and their duration to…
Q: What are the values of the slack for activities B and F?
A:
Q: days. Carl's team should be able to complete the project in
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: G This exercise contains only parts b, c, and d. b) The critical activities for the leadership…
A: The critical activities are the activities that lie on the critical path of a project. In a project,…
Q: What role does a work breakdown structure have in preventing scope creep?
A: Project management is the management in which different types of skills and knowledge are required…
Q: of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=9. A. the critical…
A: 1) Correct answer is (B) Critical Path = D-E-F duration 16 2) Correct answer is (D) A firm produces…
Q: Identify the term being described for each of the following: b. The longest time sequence of…
A: b. The critical path is the longest time sequence of activities in a project.
Q: b) The activities on the critical path are c) The total project completion time for Rafay Ishfaq's…
A: THE ANSWER IS AS BELOW:
Q: What would a project manager have to do to crash an activity? 2. Describe the meaning of slack, and…
A: Project management is a process of coordinating all processes related with a project. A crashing…
Q: Use the schedule below to answer these questions. (Assume a 5-day work week, weekends are shown as…
A: Find the Given details below: ID Task name Duration(Days) Included Weekends(Days) Predecessors…
Q: why do you think scheduling issues often cause great concern for project managers?
A: Project scheduling begins with identifying and estimating the durations for different tasks in the…
Q: Explain how to determine the slack for each activity in aproject. Why is it important for managers…
A: Slack in a project is referred to as the time margin or extent to which a particular activity stated…
Q: 1. Activities of a project are summarized in the following table. Activity Immediate Duration…
A: Hi, we are supposed to answer three subparts at a time. Since you have not mentioned which subpart…
Q: 2. Find the critical path. What is the earliest time that the project can be completed?
A: From the following table the critical path can be ascertained: ACTIVITY EXPECTED TIME…
Q: The fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in…
A: Note: As per the Bartleby guidelines only the first three parts have been answered. AOA ( Arrow to…
Q: Project ALPHA has 6 activities from A to F as follows: Activity Duration Preceded By A A A B E F E…
A: Answer: A as A is the merged activity of the correct network diagram.
Q: What does it mean for a path to have three weeks of slack? Does each activity necessarily have three…
A: Slack on the project path is important to the managers. It is the amount of time when the activities…
Q: Slack time for each of the activities is? (Activity A-G)
A: Find the given details below: Given Details: Activity Immediate Predecessor(s) Time (days) A…
Q: a) Draw the network diagram for this project b) Calculate for the slack time c) Find the critical…
A: Find the Given details below: Activity Normal Time(days) Crash Time(days) Immediate…
Q: 1. A project consists of seven activities. The precedence relationships are given in the following…
A:
Q: Determine a) The slack available of every activity. b) The critical path c) The duration of the…
A: Project network is the diagram that shows the project tasks or activities and their duration to…
Q: Describe the various purposes of using project scheduling?
A: Project management scheduling contains a list of a project related activities and deliverables,…
Q: In reference to the attached activity precedence diagram and activity times shown. (Feel free to…
A: Slack time = Slack time is the time by which a activity can be delayed , without delaying the over…
Q: (i) The backward pass in project network calculations determines the A. Latest time's activities can…
A: network diagram helps in scheduling the activities of project management. It helps in analysing the…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 4 images
- AABCDE Activity J К Predecessor None PZABUD FGHL-KL EOFICI LA C H с H J.I,K Draft PDS Identify team Kickoff team meeting Source previous rocket Identify & order missing or new materials/parts Assembly Simulation Alpha Test Beta Test Training of key people Buy food to bring Launch DITONT Duration (wks) 1 1 0 2 4 8722860 1. Show the Critical Path. Give reasons for your answer. 2. If you needed to shorten the duration of the project, which activity or activities would you shorten and why?You are assigned as a project manager to lead a new quality improvement project. Q Management is asking for a project management plan. Which of the following should you aeate FIRSTI A A process improvement plan A quality management plan CA project scope statement D A project management plan 41 193 retu ABWhat is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) NORMAL COST 8 6 6 4 ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) 8 5335 400 1,000 600 1,000 1,100 CRASH COST 450 1,100 700 1,300 1,625 IMMEDIATE PREDECESSOR(S) A, B C The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $900 (enter your response as a whole number).
- The expected times and variances for the activities for a project for Test Marketers, Inc. are given below. (Assume time is provided in days.) ID 12345678 Description Pilot production Select channels of distrib. Develop mktg. program Test market Patent Full production Ad promotion Release Predecessor None None None 1 1 4 3 2,5,6,7 t₂ 6 7 4 4 10 16 3 2 Varlance [(b-a)/6]² 34225221 10States) B E- Text Predictions: On Activity A I U 2. Given below are additional details for the Evergreen Company's construction project, i.e. three time estimates. B C D ALL E F Optimistic 0.5 ARDCCDGEe Normal 2.5 1 0.9 0.5 Most Likely 1 2 3 2 1 AaBb CcDdEe No Spacing 1 AaBbCcL AaBbCcDd. Heading 1 Heading 2 Pessimistic 2 2.5 3.5 3 1.1 1.5 a) Calculate the expected completion times and completion variances for each activity. b) What are the expected days to completion now for Evergreen? c) Compute the variance and standard deviation of the Evergreen project's completion time. d) What is the probability that the Evergreen Company's project can be completed in 6.5 days? e) What would be Evergreen Company's completion days if we needed a 95% confidence level? f) Which noncritical activities should Evergreen Company monitor closely? Why? Focus EQ1: The project manager for a specific mechanical engineering project assigns 10 different activities to complete this project successfully. These activities have several immediate predecessors as it shown in the table below Most Likely (Weeks) Immediate Optimistic (Weeks) Pessimistic Activity Description Predecessor(s) (Weeks) A 4 7 10 В A 2 20 A 8. 12 16 D B 1 3 E D, C 6. 8 22 3 4 G F 2 2 2 H. F 8 10 I E, G, H 4 8 12 1 2 3 Answer the following questions and show detailed calculations. 1. Draw the project network 2. What is the expected time for activity B? [! 3. What is the variance for activity B? 4. Based on the calculation of estimated times (expected duration), what is the critical path? 5. What is the estimated time of the critical path? 6. What is the activity variance along the critical path? 7. Based on regular CPM calculations, what is the critical path? 8. What is the probability of completion of the project before week 42?
- What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) 9 7 7 6 5 4 6 4 9 6 ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ NORMAL COST 200 800 600 1,100 1,200 CRASH COST 300 875 675 1,300 1,875 IMMEDIATE PREDECESSOR(S) (enter your response as a whole number). A, B CO O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,Using PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
- Project Management in Practice 4EDISCUSSION QUESTIONDQContrast the three types of nonnumeric project selection methods. Could any specific case combine two of them, such as the sacred cow and the oper- ating necessity, or the comparative benefits and the competitive necessity?empt.php/attempt 1839268cmki 73847 Management Sec-1 with Ja Quizzes/ Quiz 2 Duration of Dummy activity is always constant Select one: O True O FalseEX6-12 (Algo) You are creating a customer database... You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? ABCDACHSX K L Description Systems Subsystem A design Subsystem B design Subsystem C design Program A Program B Program C Subsystem A test Subsystem B test Subsystem C test Integration Integration test days. Predecessor None A A A B с D E F G H, I, J K Time (days) 7 3 1 3 5 15 5 3 3 5 3