The following represents a project that should be scheduled using CPM: TIMES (DAYS) ACTIVITY ABCDEFGH IMMEDIATE PREDECESSORS I AABCDE C,D D, E F,G b. What is the critical path? A-D-G-H B-E-G-H A-C-F-H A-D-F-H Probability a 1 2 Project completion time NTWTPNPP 1 2 1 m WWAN 00 N N NS 1 1 2 2 8 3 4 3 3 b69193nnn 11 11 11 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. 11 Answer is not complete. days d. What is the probability of completing this project within 19 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The following represents a project that should be scheduled using CPM:
ACTIVITY
A
B
C
D
E
F
G
H
IMMEDIATE
PREDECESSORS
A
A
B
C, D
D, E
F,G
b. What is the critical path?
ⒸA-D-G-H
OB-E-G-H
ⒸA-C-F-H
A-D-F-H
Probability
TIMES (DAYS)
b
Project completion time
a
1
1
2
1
1
3
1
2
m
2
2
2
8
2
4
3
3
6
9
11
9
3
c. What is the expected project completion time?
Note: Do not round intermediate calculations. Round your answer to 3 decimal places.
11
11
11
X Answer is not complete.
days
d. What is the probability of completing this project within 19 days?
Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate
calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.
Transcribed Image Text:The following represents a project that should be scheduled using CPM: ACTIVITY A B C D E F G H IMMEDIATE PREDECESSORS A A B C, D D, E F,G b. What is the critical path? ⒸA-D-G-H OB-E-G-H ⒸA-C-F-H A-D-F-H Probability TIMES (DAYS) b Project completion time a 1 1 2 1 1 3 1 2 m 2 2 2 8 2 4 3 3 6 9 11 9 3 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. 11 11 11 X Answer is not complete. days d. What is the probability of completing this project within 19 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.