Principles of Accounting Volume 2
19th Edition
ISBN: 9781947172609
Author: OpenStax
Publisher: OpenStax College
expand_more
expand_more
format_list_bulleted
Textbook Question
Chapter 8, Problem 22MC
Which of the following is a possible cause of an unfavorable material price variance?
A. purchasing too much material
B. purchasing higher-quality material
C. hiring substandard workers
D. buying substandard material
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Which of the following is a possible cause of an unfavorable material quantity variance?
A) paying more than should have for workers
B) purchasing too much material
C) hiring higher-quality workers
D) purchasing substandard material
Identify the cause of an unfavorable variance in profit.
a.Actual labor cost is lower than budget
b.Actual sales volume is higher than budget
c.Actual material cost is higher than budget
d. Actual sales price is higher than budget
Explain
What effect, if any, would you expect purchasing poor-quality materials to have on direct labour variances?
Chapter 8 Solutions
Principles of Accounting Volume 2
Ch. 8 - Why does a company use a standard costing system?...Ch. 8 - This standard is set at a level that may be...Ch. 8 - This standard is set at a level that could be...Ch. 8 - This variance is the difference involving spending...Ch. 8 - This variance is the difference involving spending...Ch. 8 - What are some possible reasons for a material...Ch. 8 - When is the material price variance unfavorable?...Ch. 8 - When is the material price variance favorable? A....Ch. 8 - What are some reasons for a material quantity...Ch. 8 - When is the material quantity variance favorable?...
Ch. 8 - When is the material quantity unfavorable? A. when...Ch. 8 - What are some possible reasons for a labor rate...Ch. 8 - When is the labor rate variance unfavorable? A....Ch. 8 - When is the labor rate variance favorable? A. when...Ch. 8 - What are some possible reasons for a direct labor...Ch. 8 - When is the direct labor time variance favorable?...Ch. 8 - When is the direct labor time variance...Ch. 8 - A flexible budget______. A. predicts estimated...Ch. 8 - The variable overhead rate variance is caused by...Ch. 8 - The variable overhead efficiency variance is...Ch. 8 - The fixed factory overhead variance is caused by...Ch. 8 - Which of the following is a possible cause of an...Ch. 8 - Which of the following is a possible cause of an...Ch. 8 - Which of the following is a possible cause of an...Ch. 8 - Which of the following is a possible cause of an...Ch. 8 - What two components are needed to determine a...Ch. 8 - What two components are needed to determine a...Ch. 8 - What elements require consideration before...Ch. 8 - What is a variance?Ch. 8 - What causes the material price variance?Ch. 8 - What causes the material quantity variance?Ch. 8 - What are some possible causes of a material price...Ch. 8 - What are some possible causes of a material...Ch. 8 - What is the direct labor rate variance?Ch. 8 - What is the direct labor time variance?Ch. 8 - What are some possible causes of a direct labor...Ch. 8 - What are some possible causes of a direct labor...Ch. 8 - How is the total direct labor variance calculated?Ch. 8 - What causes the variable overhead rate variance?Ch. 8 - What causes the variable overhead efficiency...Ch. 8 - What is the main difference between a flexible...Ch. 8 - What causes a favorable variance?Ch. 8 - What causes an unfavorable variance?Ch. 8 - When might a favorable variance not be a good...Ch. 8 - When might an unfavorable variance be a good...Ch. 8 - Identify several causes of a favorable material...Ch. 8 - Identify several causes of an unfavorable material...Ch. 8 - Identify several causes of a favorable material...Ch. 8 - Identify several causes of an unfavorable material...Ch. 8 - Identify several causes of a favorable labor rate...Ch. 8 - Identity several causes of an unfavorable labor...Ch. 8 - Identify several causes of a favorable labor...Ch. 8 - Identify several causes of an unfavorable labor...Ch. 8 - Moisha is developing material standards for her...Ch. 8 - Rene is working with the operations manager to...Ch. 8 - Fiona cleans offices. She is allowed 5 seconds per...Ch. 8 - Use the information provided to create a standard...Ch. 8 - Sitka Industries uses a cost system that carries...Ch. 8 - Use the information provided to answer the...Ch. 8 - Dog Bone Bakery, which bakes dog treats, makes a...Ch. 8 - Queen Industries uses a standard costing system in...Ch. 8 - Penny Company manufactures only one product and...Ch. 8 - ThingOne Company has the following information...Ch. 8 - A manufacturer planned to use $78 of variable...Ch. 8 - Acme Inc. has the following information available:...Ch. 8 - Acme Inc. has the following information available:...Ch. 8 - Acme Inc. has the following information available:...Ch. 8 - Bristol is developing material standards for her...Ch. 8 - Salley is developing material and labor standards...Ch. 8 - Use the following information to create a standard...Ch. 8 - Mateo makes gizmos. He would like to set up a...Ch. 8 - Smith Industries uses a cost system that carries...Ch. 8 - Lizbeth, Inc., makes ice cream. The toffee coffee...Ch. 8 - Woodpecker manufactures sawmill equipment. They...Ch. 8 - Case made 24,500 units during June, using 32,000...Ch. 8 - Eagle Inc. uses a standard cost system. During the...Ch. 8 - A manufacturer planned to use $45 of variable...Ch. 8 - Fitzgerald Company manufactures sewing machines,...Ch. 8 - Acme Inc. has the following information available:...Ch. 8 - Acme Inc. has the following information available:...Ch. 8 - Acme Inc. has the following information available:...Ch. 8 - The comptroller wants to set the standards...Ch. 8 - Stan is opening a coffee shop next to Big State...Ch. 8 - What makes a variance favorable? Give an example...Ch. 8 - April Industries employs a standard costing system...Ch. 8 - Ed Co. manufactures two types of O rings, large...Ch. 8 - The Whizbang Company makes a special type of toy....Ch. 8 - Ellis Companys labor information for September is...Ch. 8 - Breakaway Companys labor information for May is as...Ch. 8 - Power Co.s labor information for June is as...Ch. 8 - Prepare a flexible budget for overhead based on...Ch. 8 - Reddy Corporation has collected the following data...Ch. 8 - ABC Inc. spent a total of $48,000 on factory...Ch. 8 - Recompute the variances from the second Acme Inc....Ch. 8 - Sameerah is trying to determine the standard hours...Ch. 8 - Carl cleans offices. He has the following...Ch. 8 - Freidrich is working with the operations manager...Ch. 8 - A company bought 45,000 pounds of plastic pellets...Ch. 8 - Illinois Company is a medium-sized company that...Ch. 8 - Corolla Manufacturing has a standard cost for...Ch. 8 - Marymount Company makes one product. In the month...Ch. 8 - Adam Inc.s records for May include the following...Ch. 8 - Ribcos labor cost information for making its only...Ch. 8 - Use the following standard cost card for 1 gallon...Ch. 8 - Use the following standard cost card for 1 gallon...Ch. 8 - How do you balance a firms need to succeed and the...Ch. 8 - What type of firm would use standard costing? What...Ch. 8 - Is labor a true variable cost?Ch. 8 - Why would managers use a flexible budget? What...Ch. 8 - Fill in the blanks in the following flexible...Ch. 8 - Before automation became more prevalent, overhead...Ch. 8 - In your opinion, is it important that an...
Additional Business Textbook Solutions
Find more solutions based on key concepts
Communication Activity 9-1
In 150 words or fewer, explain the different methods that can be used to calculate d...
Horngren's Financial & Managerial Accounting, The Financial Chapters (6th Edition)
Basic accounting equation (Learning Objective 5) 10-15 min. Hanson Corp. ? 44,900 + 10,300 Tiny Tots Daycare In...
Financial Accounting, Student Value Edition (5th Edition)
4. JC Manufacturing purchase d inventory for $ 5,300 and al so paid a $260 freight bill. JC Manufacturing retur...
Horngren's Financial & Managerial Accounting, The Financial Chapters (Book & Access Card)
Discussion Analysis A13-41 Discussion Questions 1. How do managers use the statement of cash flows? 2. Describ...
Managerial Accounting (4th Edition)
Determine the future worth for Problem 17. Should your company purchase the dump truck?
Construction Accounting And Financial Management (4th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Which of the following is a possible cause of an unfavorable material quantity variance? A. purchasing substandard material B. hiring higher-quality workers C. paying more than should have for workers D. purchasing too much materialarrow_forwardWhich of the following is a possible cause of an unfavorable labor rate variance? A. hiring too many workers B. hiring higher-quality workers at a higher wage C. making too many units D. purchasing too much materialarrow_forwardWhat are some possible reasons for a labor rate variance? A. hiring of less qualified workers B. an excess of material usage C. material price increase D. utilities usage changearrow_forward
- What are some possible reasons for a material price variance? A. substandard material B. labor rate increases C. labor rate decreases D. labor efficiencyarrow_forwardWhich of the following is a possible cause of an unfavorable labor efficiency variance? A. hiring substandard workers B. making too many Units C. buying higher-quality material D. paying too much for workersarrow_forwardWhich of the following is the most likely explanation for an unfavorable materials usage variance and a favorable labor wage variance? a. The new labor contract increased wages. b. Higher quality materials were purchased, resulting in less waste. c. The company experience labor turnover and newer, less experienced workers were hired. d. A new supplier offered a lower price for materials.arrow_forward
- Which one of the following may account for an adverse labour efficiency variance? a. Using higher grade materials leading to lower wastage rates O b. Change in labour-market conditions between the setting of the standard and the actual event O c. Higher purchase cost of raw materials d. Using a higher grade of worker than was planned Oe. Poor supervisionarrow_forwardWhich of the following statements might cause a labor rate variance? Group of choices: Hiring of inexperienced workers Lack of supervision Faulty equipment Poor scheduling of workarrow_forwardIf a purchasing manager is able to buy direct materials required in the manufacturing of a product at a lower than ‘standard’ cost why may this result in an overall unfavorable total variance for DM’s.arrow_forward
- Management accounting uses variance analysis to explain what and why something happened in the cost of producing products. It is done by comparing actual outcomes to expected, or standard, costs. What is the expectation when the usage of raw materials unexpectedly decreases below the standard quantity used? Multiple Choice Favorable price variance Favorable quantity variance Unfavorable price variance Unfavorable quantity variancearrow_forwardWhat is a materials price variance? Describe this in your own words. Writing a formula is not a sufficient answer. Provide a real world example that would result in an unfavorable materials price variancearrow_forwardQuestion b Which of the following is a possible cause of an unfavourable materials quantity variance? • Use of inferior raw materials • Raw materials price increase • Use of a higher grade of labour than allowed for in the standard • Raw materials price decrease.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningSurvey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage Learning
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Survey of Accounting (Accounting I)
Accounting
ISBN:9781305961883
Author:Carl Warren
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
What is Risk Management? | Risk Management process; Author: Educationleaves;https://www.youtube.com/watch?v=IP-E75FGFkU;License: Standard youtube license