Textbook Question
Chapter 8, Problem 15E
Calculating factory
The standard capacity of a factory is 8,000 units per month. Cost and production data follow:
Calculate the amount of factory overhead allowed for the actual volume of production each month and the variance between budgeted and actual overhead for each month.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionChapter 8 Solutions
Principles of Cost Accounting
Ch. 8 - How does a standard cost accounting system work,...Ch. 8 - What is the difference between the standard cost...Ch. 8 - Prob. 3QCh. 8 - What are the specific procedures on which a...Ch. 8 - How are standards for materials and labor costs...Ch. 8 - What is a variance?Ch. 8 - How do price and quantity variances relate to...Ch. 8 - How do rate and efficiency variances relate to...Ch. 8 - Prob. 9QCh. 8 - How does a materials purchase price variance...
Ch. 8 - Prob. 11QCh. 8 - Prob. 12QCh. 8 - When a company uses a standard cost system, are...Ch. 8 - What two factors must be considered when breaking...Ch. 8 - What might cause the following materials...Ch. 8 - What might cause the following labor variances?
An...Ch. 8 - Prob. 17QCh. 8 - Prob. 18QCh. 8 - Prob. 19QCh. 8 - Prob. 20QCh. 8 - When does a flexible-budget variance occur?
Ch. 8 - Why is it important to determine flexible-budget...Ch. 8 - Prob. 23QCh. 8 - What is the significance of a production-volume...Ch. 8 - If production is more or less than the standard...Ch. 8 - At the end of the current fiscal year, the trial...Ch. 8 - What variances from the four-variance method are...Ch. 8 - What is the primary difference between the...Ch. 8 - What are the four variances in the four-variance...Ch. 8 - In all of the exercises involving variances, use F...Ch. 8 - Prob. 2ECh. 8 - Prob. 3ECh. 8 - Prob. 4ECh. 8 - Prob. 5ECh. 8 - Computing materials variances D-List Calendar Co....Ch. 8 - Computing labor variances LIFT Inc. manufactures...Ch. 8 - Standard cost summary; materials and labor cost...Ch. 8 - Computing labor variances Fill in the missing...Ch. 8 - Standard unit cost and journal entries The normal...Ch. 8 - Making journal entries Assume that during the...Ch. 8 - Using variance analysis and interpretation Last...Ch. 8 - Using variance analysis and interpretation Last...Ch. 8 - Journalizing standard costs in two departments...Ch. 8 - Calculating factory overhead The standard capacity...Ch. 8 - Determining Budgeted Overhead The overhead...Ch. 8 - Calculating factory overhead: two variances Munoz...Ch. 8 - Calculating factory overhead: two variances...Ch. 8 - The normal capacity of a manufacturing plant is...Ch. 8 - Calculating amount of factory overhead applied to...Ch. 8 - Georgia Gasket Co. budgets 8,000 direct labor...Ch. 8 - (Appendix) Calculating factory overhead: four...Ch. 8 - (Appendix) Calculating factory overhead: three...Ch. 8 - Materials and labor variances Branca Inspections...Ch. 8 - Materials and labor variances Fausto Fabricators...Ch. 8 - Zippy Inc. manufactures a fuel additive, Surge,...Ch. 8 - Calculation of materials and labor variances
Fritz...Ch. 8 - High-End Products Inc. uses a standard cost system...Ch. 8 - RDI Products Co. manufactures a variety of...Ch. 8 - The standard cost summary for the most popular...Ch. 8 - Carlo Lee Corp. has established the following...Ch. 8 - USD Inc. has established the following standard...Ch. 8 - Allocation of variances
Costa Brava Manufacturing...Ch. 8 - On May 1, Athens Inc. began the manufacture of a...Ch. 8 - The standard specifications for an electric motor...Ch. 8 - Cardiff Inc. manufactures men’s sport shirts for...Ch. 8 - Fargo Co. manufactures products in batches of 100...Ch. 8 - Prob. 15PCh. 8 - (Appendix) Overhead variances—four variance
Mobile...Ch. 8 - Shinto Corp. uses a standard cost system and...Ch. 8 - Kamen Manufacturing Co. estimates the following...Ch. 8 - Prob. 19PCh. 8 - Jillian Manufacturing Inc. manufactures a single...Ch. 8 - Cost and production data for Binghamton Beverages...
Additional Business Textbook Solutions
Find more solutions based on key concepts
18. What is the calculation for return on assets (ROA)? Explain what ROA measures.
Horngren's Financial & Managerial Accounting, The Financial Chapters (Book & Access Card)
BE1-7 Indicate which statement you would examine to find each of the following items: income statement (IS), ba...
Financial Accounting
Preparing Financial Statements from a Trial Balance The following accounts are taken from Equilibrium Riding, I...
Fundamentals of Financial Accounting
E6-14 Using accounting vocabulary
Learning Objective 1, 2
Match the accounting terms with the corresponding d...
Horngren's Accounting (11th Edition)
Based on your answers to the above questions, should Lockwood invest in the machinery?
Horngren's Financial & Managerial Accounting, The Managerial Chapters (6th Edition)
Place the letter of the appropriate accounting cost in Column 2 in the blank next to each decision category in ...
Fundamentals of Cost Accounting
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Georgia Gasket Co. budgets 8,000 direct labor hours for the year. The total overhead budget is expected to amount to 20,000. The standard cost for a unit of the companys product estimates the variable overhead as follows: The actual data for the period follow: Using the four-variance method, calculate the overhead variances. (Hint: First compute the budgeted fixed overhead rate.)arrow_forwardIf a factory operates at 100% of capacity one month, 90% of capacity the next month, and 105% of capacity the next month, will a different cost per unit be charged to the work-in-process account each month for factory overhead assuming that a predetermined annual overhead rate is used?arrow_forwardFlexible budget for factory overhead Presented below are the monthly factory overhead cost budget (at normal capacity of 5,000 units or 20,000 direct labor hours) and the production and cost data for a month. The predetermined overhead rate is based on normal capacity. Required: 1. Assuming that variable costs will vary in direct proportion to the change in volume, prepare a flexible budget for production levels of 80%, 90%, and 110% of normal capacity. Also determine the predetermined factory overhead rate at each level of volume in both units and direct labor hours. 2. Prepare a flexible budget for production levels of 80%, 90%, and 110%, assuming that variable costs will vary in direct proportion to the change in volume, but with the following exceptions. (Hint: Set up a third category for semi-variable expenses.) a. At 110% of capacity, another supervisor will be needed at a salary of 24,000 annually. b. At 80% of capacity, the repairs expense will drop to one-half of the amount at 100% capacity. c. At 80% of capacity, one part-time maintenance worker, earning 10,000 a year, will be laid off. d. At 110% of capacity, a machine not normally in use and on which no depreciation is normally recorded will be used in production. Its cost was 12,000, it has a 10-year life, and straight-line depreciation will be taken.arrow_forward
- Direct materials and direct labor variance analysis Lenni Clothing Co. manufactures clothing in a small manufacturing facility. Manufacturing has 25 employees. Each employee presently provides 40 hours of productive labor per week. Information about a production week is as follows: Instructions Determine (A) the standard cost per unit for direct materials and direct labor; (B) the price variance, quantity variance, and total direct materials cost variance; and (C) the rate variance, time variance, and total direct labor cost variance.arrow_forwardDirect labor hours are estimated as 2,000 in Quarter 1; 2,100 in Quarter 2; 1,900 in Quarter 3; and 2,300 in Quarter 4. Prepare a manufacturing overhead budget using the information provided.arrow_forwardUsing High-Low to Calculate Predicted Total Variable Cost and Total Cost for Budgeted Output Refer to the information for Pizza Vesuvio on the previous page. Assume that this information was used to construct the following formula for monthly labor cost. TotalLaborCost=5,237+(7.40EmployeeHours) Required: Assume that 675 employee hours are budgeted for the month of September. Use the total labor cost formula for the following calculations: 1. Calculate total variable labor cost for September. 2. Calculate total labor cost for September.arrow_forward
- A company estimates its manufacturing overhead will be $840,000 for the next year. What is the predetermined overhead rate given each of the following Independent allocation bases? Budgeted direct labor hours: 90,615 Budgeted direct labor expense: $750000 Estimated machine hours: 150,000arrow_forwardMarymount Company makes one product. In the month of April, it made 3,500 units. Workers were paid $32 per hour for labor, for a total of $718,848. The standard hours per unit are 6.4, and the standard labor wage rate is $38.40 per hour. A. What are the actual hours worked? B. What are the standard hours for the units made? C. What is the direct labor rate variance for April? D. What Is the direct labor time variance for April? E. What is the total direct labor variance for April?arrow_forwardCase made 24,500 units during June, using 32,000 direct labor hours. They expected to use 31,450 hours per the standard cost card. Their employees were paid $15.75 per hour for the month of June. The standard cost card uses $15.50 as the standard hourly rate. A. Compute the direct labor rate and time variances for the month of June, and also calculate the total direct labor variance. B. If the standard rate per hour was $16.00, what would change?arrow_forward
- Calculating amount of factory overhead applied to work in process The overhead application rate for a company is 2.50 per unit, made up of 1.00 for fixed overhead and 1.50 for variable overhead. Normal capacity is 10,000 units. In one month, there was an unfavorable flexible budget variance of 200. Actual overhead for the month was 27,000. What was the amount of the budgeted overhead for the actual level of production?arrow_forwardBusiness Specialty, Inc., manufactures two staplers: small and regular. The standard quantities of direct labor and direct materials per unit for the year are as follows: The standard price paid per pound of direct materials is 1.60. The standard rate for labor is 8.00. Overhead is applied on the basis of direct labor hours. A plantwide rate is used. Budgeted overhead for the year is as follows: The company expects to work 12,000 direct labor hours during the year; standard overhead rates are computed using this activity level. For every small stapler produced, the company produces two regular staplers. Actual operating data for the year are as follows: a. Units produced: small staplers, 35,000; regular staplers, 70,000. b. Direct materials purchased and used: 56,000 pounds at 1.5513,000 for the small stapler and 43,000 for the regular stapler. There were no beginning or ending direct materials inventories. c. Direct labor: 14,800 hours3,600 hours for the small stapler and 11,200 hours for the regular stapler. Total cost of direct labor: 114,700. d. Variable overhead: 607,500. e. Fixed overhead: 350,000. Required: 1. Prepare a standard cost sheet showing the unit cost for each product. 2. Compute the direct materials price and usage variances for each product. Prepare journal entries to record direct materials activity. 3. Compute the direct labor rate and efficiency variances for each product. Prepare journal entries to record direct labor activity. 4. Compute the variances for fixed and variable overhead. Prepare journal entries to record overhead activity. All variances are closed to Cost of Goods Sold. 5. Assume that you know only the total direct materials used for both products and the total direct labor hours used for both products. Can you compute the total direct materials and direct labor usage variances? Explain.arrow_forwardFactory overhead cost variance report Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 20,000 hours for production: Tannin has available 25,000 hours of monthly productive capacity in the Trim Department under normal business conditions. During July, the Trim Department actually used 22,000 hours for production. The actual fixed costs were as budgeted. The actual variable overhead for July was as follows: Construct a factory overhead cost variance report for the Trim Department for July.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
- Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY