Answer to Problem 4.4P
The shredder energy requirement for shredding is
Explanation of Solution
Given:
The fraction of feed retained on sieve is shown in the table below:
Sieve Size |
Fraction of Feed Retained on the Sieve |
Assume, from the figure that the axis is a logarithmic scale then for
Calculation:
Write the equation to calculate the shredder energy requirement for shredding.
Here, the shredder energy is
Write the equation to calculate the slope
Substitute
Write the equation to calculate the slope
Substitute
The slope
Calculate the shredder energy requirement for shredding.
Substitute
Conclusion:
Thus, the shredder energy requirement for shredding is
Want to see more full solutions like this?
- Plese show your solution on a paper with FBDarrow_forwardFor preparing PCC, would you prefer round and smooth aggregate or rough and angular aggregate? Briefly explain why (no more than two lines). b. For preparing HMA, would you prefer round and smooth aggregate or rough and angular aggregate? Briefly explain why (no more than two lines).arrow_forwardCivil Engineering Quest 1: Calculate the moment of the force P about the axis AD using (a) point A as the moment center (b) point D as the moment center 6 ft 3 ft P=240 lb 2 ft Solution Quest 2: 1, Define: PC, PCB 2. What are the quality requirements of raw matenarrow_forward
- For material testing,Take one destructive and one non-destructive test and explain how both test procedures produce useful results.arrow_forwardA 1.2-ff3 block of aluminum is tied to a piece of cork (SG=0.22), as shown. What volume of cork is required to keep the aluminum (SG=2.7) from sinking in castor oil (SG=0.96)?arrow_forwardThe aggregates are placed in a cylindrical container weighing 0.3 kg with a base circumference of 0.18π ft. and a height of 1.4 ft. Find the unit weight of the aggregates.arrow_forward
- Solid Waste EngineeringCivil EngineeringISBN:9781305635203Author:Worrell, William A.Publisher:Cengage Learning,