Your project is divided into five major subprojects. Subproject “P” involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject “S” supplier specifications. These involve engineering details for how the product will perform.      The individual components that make up the product are the focus of subproject “D.” Subproject “I” brings all the components together, and a working prototype is built and tested.      Finally, in subproject “V,” suppliers are selected and contracts are negotiated. MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS) Product Specifications (P)       Market research P1

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.1SA
icon
Related questions
Question

 Your project is divided into five major subprojects. Subproject “P” involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These details are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject “S” supplier specifications. These involve engineering details for how the product will perform.
     The individual components that make up the product are the focus of subproject “D.” Subproject “I” brings all the components together, and a working prototype is built and tested.
     Finally, in subproject “V,” suppliers are selected and contracts are negotiated.

MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS)
Product Specifications (P)      
Market research P1 6
Overall product specifications P2 P1 4
Hardware P3 P2 6
Software P4 P3 6
Supplier specifications (S)      
Hardware S1 P4 5
Software S2 P4 6
Product design (D)      
Battery D1 S1 1
Display D2 S1 6
Camera D3 S1 1
Outer cover D4 D1, D2, D3 4
Product integration (I)      
Hardware I1 D4 3
User interface I2 D2 6
Software coding I3 I2 6
Prototype testing I4 I1, I3 5
Subcontracting (V)      
Suppliers selection V1 S1 ,S2 10
Contract negotiation V2 I4, V1 2
 

 

a. Calculate the start and finish times for each activity.

b.Determine the minimum number of weeks for completing the project.

c. Find the activities that are on the critical path for completing the project in the shortest time.

  • P1-P2-P3-P4-S1-D1-D4-I1-I4-V2
  • P1-P2-P3-P4-S1-D2-D4-I1-I4-V2
  • P1-P2-P3-P4-S1-D3-D4-I1-I4-V2
  • P1-P2-P3-P4-S1-D2-I2-I3-I4-V2

 

Expert Solution
steps

Step by step

Solved in 5 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning