Normal Activity Predecessor Time A B C D E 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? G H JA A B C E D A H 18 12 15 3 7 8 12 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $12,000 5 $18,000 19 $22,000 $9,000 2 $15,000 15 $5,000 S $13,000 $20,000 8 $45,000 4 $8,000 $23,000 $32,000 $56,000

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
B/U
pe
Activity
A
B
D
11. A project has the activity duration and cost information indicated in the table where all
times are in weeks. There is a penalty of $4,000 per week for every week the project
exceeds 37 weeks. What is the lowest total cost for completing this project?
Predecessor Time
18
11
A
A
B
C
E
D
Normal
A
H
12
15
3
19
Asbe de ABC' AMBBC RACE AB
7
8
12
6
Normal
Cost
Crash Time Crash Cost
$22,000
$32,000
$62,000
$18,000
$35,000
$8,000
$23,000
$32,000
$56,000
$12,000 5
$18,000
19
$22,000
$9,000
$15,000
$5,000
$13,000
$20,000
$45,000
2
5
4
Transcribed Image Text:B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.