QI: Given the information below, draw the network (AOA) and find the probability of finishing the job in (40) weeks? Solve using PERT. Activity notation Weeks 1-2 2-3 2-4 2-5 3-6 4-7 5-7 6-8 7-8 8-9 2,7,8 5,6,9 3,7,8 4,5,6 6,9,10 6,8,11 4,6,7 5,7,10 4,8,9 4,7,9 [50% ]
Q: Q3. Construct network and do the numbering according to Fulkerson's rule for the following: Activity…
A: Each node is addressed by a circle and numbered by utilizing Fulkerson's Rule. Following advances…
Q: Activity 2: Consider the following immediate preceding activity table. Draw the network and…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: answer items f and g
A: A Small Introduction about Critical Path In project management, a critical path is the…
Q: e) Draw manually the appropriate network diagram (using PDM) and then find (and also provide as a…
A: Below is the solution:-
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A: Following format considered for network diagram: Early Start(ES) Duration Early Finish (EF)…
Q: H.W For the following activities, draw the network diagram and by using forward and backward pass,…
A: Given data is
Q: The utility data for a network are given below. Determine the total, free, independent and…
A: Given data is
Q: Fill the table below using the Activity-on-Arrow (A-o-A) network given and answer the questions.…
A:
Q: Consider the following project consisting of activities given in the table. For the activity…
A: a) Find the Duration and Variance calculations below: Note: Used formula mentioned in the…
Q: Draw the Project Network
A: A network diagram is a visual picture of a project which helps to identify the activity relationship…
Q: b) - Draw the Activity-on-Node (AON) diagram using the following representation for every node:…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: Construct a network diagram and identify the critical path for the following project sch Si no.…
A: The network diagram is the pictorial representation of all the activities in the project based on…
Q: For a particular project, consider following list of Activities, their duration in Days and their…
A: Given data is,
Q: For the following network, figure out the total floats and the critical path assuming interruptible…
A: Find the Given details below: Given details: Activity Duration A 4 B 3 C 8 D 7 E 6…
Q: Using the data in the following table: a) Draw the network diagram b) List the network paths, the…
A: Given data is
Q: Draw the network for this project.
A: The project network diagram is the graphical representation of the project tasks or activities and…
Q: What are the objectives of construction management?
A: NOTE: We are allowed to do one question only at a time. Please post the rest questions individually…
Q: For the construction project represented by the activity network as 16 points shown below. Find one…
A:
Q: Consider the following data for a project to install a new server at the Northland Pines High…
A: Given Information:
Q: Develop an activity schedule for this project using early and late start and finish times, compute…
A: A forward and backward passing network diagram including 5 different time dimension for a project…
Q: Below is the network diagram from a project: B(2) D(5) A(2) F(3) C(5) E(3) What is the slack for…
A: A project network is the visual representation of the project activities and their respective…
Q: Clean Up Project in Karbabad, what will be its completion time? Your answer should show the network…
A: The project completion time is depicted by the critical path of the project. It is taken as the path…
Q: What is the critical path of the network?
A:
Q: Consider the following information for a project to add a drive-through window at Crestview Bank.…
A:
Q: Given the following highway rerouting project, refer to the two pics please :)) (a) Draw the…
A: Given data is
Q: 1. Alpha Team received an assignment from the Company to work on a bridge construction project. Budi…
A: ES -Early start time LS - Late start time EF - Early finish time LF - Late finish time ES =…
Q: You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. a)…
A: Below is the solution:-
Q: QI/ The following table shows the activities of a construction project, sequences and estimated…
A:
Q: For the project detailed in the table below: a) Draw the Activity on Node (AON) network diagram…
A: Activity Immediate Predecessors Duration A - 4 B - 6 C A,B 7 D B 8 E B 5 F C 5 G D 7…
Q: For the following schedule, draw the node network, perform the CPM calculations, mark the critical…
A: Given data is
Q: Project planners sought judgment of various knowledgeable engineers, vendors and foremen and have…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: 9.4. (LO 9.5) Construct a network from the information in the following table, identify all the…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: Use the following information in a table about the activities of an information technology project…
A: Activity Predecessors Days A -- 4 B A 5 C A 6 D B 5 E B, C 3 F D, E 7
Q: You are given the activity information below and the activity-on-node precedence diagram for a…
A: An organization chart has numerous ways beginning from one point and finishing at another point.…
Q: The following information is available about a project toorganize an event to honor the mayor of…
A: Given data
Q: Make a clear and neat sketch of the network specified belowusing precedence notation. On the…
A: Activity Duration EST EFT LST LFT TF(LFT-EFT) A 2 0 2 0 2 0 B 4 2 6 2 6 0 C 7 2 9 5 12 3 D 3…
Q: (b) Identify all of the paths on the network diagram and note how long they are, using Figure 6- 8…
A:
Q: From this PERT/CPM network, determine the list of activities and their predecessors. Activity…
A:
Q: From the following schedule, draw the precedence network, perform the CPM calculations, mark the…
A: Here, Network Diagram is produced using forward path method and backward path method, in forward…
Q: a. Use the Table 1 above to develop a network diagram. b. Calculate the Early Start (ES), Early…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Consider a project for which the following activities and time estimates in weeks apply activity…
A: Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: The activity table is given below 22/05/ Activity Predecessor Duration ES 0-1 Clear site 3 0 1-2…
A: Find the Given details below: Activity Activity Duration ES LF 0-1 A 3 0 3 1-2 B 2 3 5 2-3…
Q: (ii) Indicate the maximum crew size in each case (iii) Re-schedule the activities for smooth…
A: Note: As per the Bartleby guidelines only three parts have been answered:
Q: Construct the network for the following project and determine the following i) Critical Path ii)…
A: Critical path is defined as the path that defines the longest duration of activities, pertaining to…
Q: Read the following set of activities carefully. The precedence of all activities is finish to start.…
A: The program evaluation and review technique (PERT) is a statistical device utilized in undertaking…
Q: Reliable Garage is completing production of the J2000 kit car.The following data are available for…
A:
Q: For the activity times and network model below, What is the expected completion time? ________ What…
A: Here is the network diagram with activity & time duration :
Step by step
Solved in 5 steps with 4 images
- A B с D E FL ד G H J K L M N P R S T U V 1 On Week 3 Forecast 4 2 a) Smell Fresh Customer Orders hand 1 2 20 20 5 3 5 PAB 20 50 30 3222 4 5 6 7 8 Problem 6: Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Partially-completed MPS time-phased record is given below. 20 30 30 30 30 30 Week 10 30 50 20 40 10 Item: Smell Fresh On hand 1 6 Available to Promise 7 MPS 50 50 50 50 Forecast 20 8 MPS lot size = 50 9 20 10 On Week hand 2 3 4 5 6 7 8 9 20 53 43 78 30 30 30 30 30 3220 2233 -250 30 10 30 50 6 8 45 12 13 14 PAB 15 11 b) Smell Fresh Forecast Customer Orders Available to Promise 16 MPS 17 MPS lot size=50 18 19 20 21 23 24 222 Orders Projected available balance Available-to-promise MPS MPS Lot Size = 50. 50 20 40 10 50 50 50 a) Complete the MPS time-phased record (the first table on the left). The following events occurred during week 1: • Actual demand during week 1 was 25 units. • Marketing forecasted that 40 units would be needed for…Normal Time Problem 1 You are the manager of a project to improve a billing process at your firm. The following table contains the data you will need to conduct crashing of the project duration. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after Week 12. Activity Immediate Predecessor(s) Crash Time (weeks) Normal (Direct) Cost Crash Cost (weeks) ($) ($) A 4 1 5,000 8,000 B 5 2 8,000 11,000 C A 1 1 4,000 4,000 Ꭰ B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F Ꭰ 7 6 4,000 7,000 What is the optimum choice for project duration?1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?
- What is a precedence diagramand what are its various components? Briefly explain.Which of the following information is required from the client for 'preliminary estimating'? Select the BEST combination. Select one: а. Site location, risk register, project requirements, budget constraints. b. Site location, key dates, sustainability strategy, budget constraints. Site location, building use, risk register, budget constraints. ос. O d. Site location, building use, key dates, budget constraints.Can i get help with the question below please and thank you 16) This could be a rover, probe/satellite, manned mission, telescope, etc. This mission must be accomplished using technology that is available today (no Warp or Epstein drives) and must be accomplished within your lifetime. Your mission will not be a copy of a real mission. Constraints: ▪ Answer using the underlined subheadings at each point below (Mission Objective, Target, Instrumentation), marks will be deducted for poorly organized answers. ▪ You target must be reachable by whatever you are sending within a human lifetime (~75 years), it would be nice to visit Gliese 581c, but it is 20 light years from Earth so for now it is unreachable. What this means is that you are constrained to our solar system except for telescopes that peer into the universe or a probe getting to interstellar space. ▪ If your mission includes sending humans, then we need to estimate a reasonable limit on how far we can send humans. For our…
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: 3.8 IMMEDIATE АCTIVITY PREDECESSOR(S) TIME (DAYS) A 2 5 1 10 A, D 3 F G E, F 8 a) Develop an AON network for this problem. b) What is the critical path? c) What is the total project completion time? d) What is the slack time for each individual activity? PX 6. B. B. E.How Can You Get to a Backlog of over 100 Projects? There are never enough resources to get everything done." Backlogs build over time. Sacred cow projects get included in the selection system. Projects proposed from people who have left the airline stil reside in the project portfolio. Non-value-added projects somehow make their way into the project portfolio. Soon the queue gets longer. With everyone in IT working on too many projects concurrently, project completion and productivity are slow. Which Projects Remain? To cut the number of projects, the steering committee used a weighting scheme that reflected the airline's priorities, which were: fly safe, generate revenue, reduce costs, and customer service. The weighting scheme easily weeded out the fluff. Coady noted that "by the time you get to the 20s the margin of differentiation gets narrower and narrower." Of the remaining projects, project sponsors had to have solid justification why their project is important. Reduction of the…A company is setting up an assembly line to produce 90 units per hour. The table below identifies the work elements, times, and immediate predecessors. Work Element Time (Sec.) Immediate Predecessor(s) A 25 - B 18 A C 20 A D 5 B, C E 12 C F 8 E G 16 D, F H 12 G Use one of the heuristic decision rules described in Table below to balance the assembly line so that it will produce 90 units per hour. Clearly state the decision rule you use and complete the below table using the selected rule. Decision Rule Logic Longest work element Picking the candidate with the longest time to complete is an effort to fit in the most difficult elements first, leaving the ones with short times to “fill out” the station. Shortest work element This rule is the opposite of the longest work element rule because it gives preference in workstation assignments to those work elements that are quicker. It can be tried…
- Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Time (weeks) Immediate Time (weeks) Immediate Activity b Predecessor(s) Activity b Predecessor(s) a m a A 4 9. 12 G 3 3 С, Е B 1 9. 24 A H 2 2 2 F 12 16 A 5 F D, G, H I, J 7 10 A J 6. 12 E 1 4 В 3 3 4 F 6. 8. 21 С, Е a) The expected (estimated) time for activity C is 12.00 weeks. (Round your response to two decimal places.) b) The variance for activity C is 1.78 weeks. (Round your response to two decimal places.) c) Based on the calculation of the estimated times, the critical path is A- B - E-F-H-J-K. d) The estimated time for the critical path is 44.99 weeks. (Round your response to two decimal places.) e) The activity variance along the critical path is 24.00 weeks. (Round your response to two decimal places.) f) Using the standard normal table, the probability that Hopkins Hospitality will finish the project in 40 weeks or…Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 4 B − 6 C − 1 D B 10 E A, D 5 F C 5 G E, F 8 This exercise contains only parts b, c, and d. Part 2 b) The critical activities for the leadership training program development project are ▼ B - D - E - G C - F - G A - E - G . Part 3 c) The project length for the leadership training program development project = enter your response here days. Part 4 d) Slack time for each of the activities is: Part 5 Part 6 Part 7…Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 2 B − 6 C − 1 D B 10 E A, D 3 F C 6 G E, F 8 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are ▼ C - F - G A - E - G B - D - E - G . c) The project length for the leadership training program development project = enter your response here days. d) Slack time for each of the activities is: Activity Slack Time A enter your response here B enter your response…