Q1:- The timetable for one of the projects was as in Table No. (1), answer the following: 1- Draw the sagittal wireframe of the project 2- Find the late start time for the event numbered (5). 3- The time limit for the early end of the activity No. (9) 4-Project completion time 5- select the critical path
Q: A plumber has decided to use the techniques of project management in order to plan a job. He knew…
A: The critical path method in project management is the longest set of activities that must be…
Q: Q1) The project schedule has the following characteristics: Activity Time (weeks) Activity…
A: Given information, Activity Predecessors Durations A 10 B 7 C B 5 D B 6 E A 9…
Q: A2 A4 A5 A3 Task Duration (days) 3 A1 3 A2 A3 1 A4 A5 days What is the late finish time for activity…
A: Using the Forward Path Early Start of the activity = Early Finish of predecessor activity Early…
Q: For the small project with the relationships shown below. Activity IPA's Duration (Day) A 5 B 7 4 D…
A: An activity-on-node diagram is a visual representation of the network of an entire project schedule.…
Q: Q1: For the project listed below, find the following items: 1- Total project finishing time 2-…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: Q1: For activities shown in table below, find the new time of project after updating, if the project…
A: Given data is
Q: (b) By referring to information in Table 1, determine the critical path, non-critical paths, and…
A: A Small Introduction about Critical path In project management, a critical path is the succession…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Note: - As we can answer only three subparts, the first three(a, b, and c) will be answered. If…
Q: SESSION 2– Individual exercise (for marks) Given the following activity precedence table, please…
A: The question is related to Critical Path Analysis. The details are given.
Q: 1. Draw the network diagram. 2. Calculate the expected duration and variance of each activity. 3.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A:
Q: 01) The utility data for a network are given below: Activity Duration (Days) 0-1 1-2 8 1 -3 10 2-4…
A: Note: - Since we can answer only up to 3 subparts we will answer subparts 1, 2, and 3 for your…
Q: CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT…
A: Project management is described as a process through which a project, the resources of a project are…
Q: I need a project scope management plan and not a list of what should be included in the plan
A: A Project Scope Management Plan outlines the processes involved in executing your project and serve…
Q: Q1- The schedule for one of the projects was as in Table No. (1), answer the following- 1- Draw the…
A: Below is the solution:-
Q: ID Immediate Time (weeks) Predecessor A 6 B. 4 3. D. A, B, C 7 4. F D 2 H. ID Cost by week (in…
A:
Q: Give data of a project. Project manager checks the project at the end of week 10th Manpowers/ weeks…
A: Cost Variance (CV = EV - AC) Cost Performance Index (CPI = EV/AC) Schedule Variance (SV = EV -…
Q: The activities necessary for the completion of this project are listed in the following table:…
A: Since you have posted a question with multiple sub-parts, we will solve the subparts asked by you.…
Q: CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT…
A: Project management: It illustrates the method of managing the whole project work to accomplish some…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: Hi, we are supposed to answer three subparts at a time. Since you have not mentioned which subpart…
Q: A2 A4 A5 Task Duration (days) 3 A1 A2 A3 3 Aa A5 days What is the late finish time for activity A,?
A: Using the Forward path, Early Start of the activity = Early Finish of predecessor activity Early…
Q: Ql: For activities shown in table below, find the new time of project after updating, if the project…
A:
Q: Table 7.8 contains data for the installation of new equipment in a manufacturing process at Excello…
A:
Q: The first question: The part of a construction project whose activities are shown in Table No. 1…
A:
Q: В- using the table below, Activity Predecessor Duration A A A D E 1 В E,C F D,B 1- How many paths…
A: The project network diagram is the visual representation of project tasks and their duration to…
Q: An activity, A, has two succeeding activities, B and C. Given the following information, determine…
A: Option C - 33
Q: Create the project management plan, project charter, enterprise environmental factors (EEFs), and…
A: Disclaimer: Since you have asked multiple question, so we will solve the first question for you. If…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: The critical path method is used to calculate the duration of the project by sequentially arranging…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (x) = 40 weeksDesired completion time (μ) = 40 weeks or…
Q: A project has the following activities, with specified precedents and expected durations (in hours).…
A: A network diagram is a diagram that shows the visual form of the project activities and their…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (μ)= 40 weeksDesired completion time (x) = 46 weeks or…
Q: Enrichment Exercise 7.2 Promoter of championship boxing match must perform the task shown in the…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each…
A: The project network is the visual representation of the project activities and their durations to…
Q: Development of Version 2.0 of a particular accounting software product is being considered by Jose…
A: The critical path method is based on mathematical calculations to calculate the duration of the…
Q: 1) Build a quality management plan.
A: A Small Introduction to Quality Management Quality management is the demonstration of supervising…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Mean (x) = 40 weeks Desired completion time (μ) = 40 weeks Variance (σ2) = 9 weeks
Q: Q4: - The network diagram of one of the projects and its data as in Table No. (4), so if want to…
A: Below is the solution:-
Q: Q3: Draw the network diagram and determine the critical path for the following project: Activity…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: What would a project manager have to do to crash an activity? 2. Describe the meaning of slack, and…
A: Project management is a process of coordinating all processes related with a project. A crashing…
Q: CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT…
A: The success of any project is dependent on careful planning and the collaboration of a project…
Q: NORMAL CRASH TIME NORMAL CRASH COST TIME IMMEDIATE ACTIVITY (WEEKS) (WEEKS) COST PREDECESSOR(S) A 4…
A: Answer: we can see that for the mentioned project there are seven activities A, B, C, D, E, F, G. In…
Q: What is the slack time for activity A? 7 5 3 0
A: Formula:
Q: Predecessors C, F 9. Activity A B. H, I None (Start) B, J D D. C. H. G\ Construct a CPM network for…
A: Edge Node1 → Node2 D 1→2 C 2→3 F 2→4 d 3→4 G 3→6 H 3→7 A 4→5 J 5→8 I 6→7 B 7→8…
Q: Immediate Activity Predecessor Time (days) 8 в 20 33 18 D E 20 F B B.C 10 H D EF G, H, I 4 (End) a)…
A: A network diagram is a visual representation of a project which helps to identify the project…
Q: Question 2…
A: We know in Project Management, Variance may be a measure of a deviation from the projected value.…
Q: Q2. Consider the following data summarizing the details of a project involving 12 activities.…
A:
Q: Q2,A project network diagram with activities and their durations (days) is given below. A H 2 10…
A: In assembly line balancing, each task is assigned to a workstation in order to meet the specified…
Q: What is the slack time for Activity F and the late start for Activity H?
A: Below is the solution:-
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: Q1: A project consisting of the following activities: ML KTJIH GFE D CB A K J HE GF D.C D.C D.C A BB…
A:
Step by step
Solved in 2 steps with 1 images
- Activities/Assessments: Activity 12: Individual Given the activities of a project; their optimistic (t.), most likely (tm) and pessimistic (tp) time estimates; and their immediate predecessors shown below: 1. When is the earliest project completion? 2. Which activities are critical (should not be delayed)? 3. Which activities are noncritical (can be delayed)? 4. How long can each of the activities be delayed without delaying the whole project (maximum slack)? Activity Times, months tp 13 Immediate Maximum Slack, Activities Predecessors to tm te months A 1 4 A 4 7 16 A 2 2 D C 4 6 14 E 1 3 5 F E 13 10 13 H G 7 14 В, D F, H, I I 1 1 J 16 25 M7613Q4. Answer the following questions (a-h), based on the provided project Gantt Chart. The red line indicates the current evaluation time. Activities A B D E F G H W1 W2 W3 W4 W6 W7 W8 W9 W10 W11 W12 Actual Schedule Baseline Schedule a) Explain what the 'Baseline Schedule' represents. ( b) Did the project start on time? Explain why/why not. c) Mention the activity/activities that started on time. " d) Mention the activity/activities that finished on time. I e) Mention the activity/activities that was/were implemented as per the plan.. f) Mention the activity/activities that required less time to be implemented than planned. g) Mention the activity/activities that has/have started but not completed yet h) Mention the activity/activities that hasn't/haven't started yet., CPERT-CPM 1. Consider a project involving the following activities and precedence relationship. The cost of each activity is listed. The following activity time estimates have been provided for a preparation involving an MIS project. a. Draw the AON and AOA Diagram. b. Perform a Program Evaluation and Review Technique (PERT) to determine the expected total duration of the project. [Note: Use the diagramming convention agreed in class and tabulate the results for each activity's ES, EF, LS, LF, slack time and indication if it's in the critical path Note: Expected (Ave Time) = (0ptimistic Time + 4*Most Likely Time + PessimisticTime) / 6 = ( OT + 4MLT + PT ) / 6 c. If the project exceeds 11 weeks, there is an additional miscellaneous costs around Php 30,000. Will the company opt to speed up the project? Activity Predecessors Optimistic Most Pessimistic Crash Normal Crashed Likely Time Cost Cost A 2 4 6. 2 11,000 6,000 3,000 7,000 4,000 13,000 9,000 4,000 5,000 3,000 3 17.000 В 1 3 5 1…
- A project consist of 5 activities A,B,C,D,E with ES, EF, LS and LF of A (0, 6, 9, 15); B (0, 7, 0, 7); C (6, 13, 15, 22); D (7, 13, 7, 13); E (13, 22, 13, 22). Normal Time (in month), Crash time (in month), Normal cost (in million Rp), Crash cost (in million Rp) from each activity are A (6, 4, 20, 24); B (7, 5, 30, 35); C (7, 6, 10, 13); D (6, 4, 20, 26); E (9, 8, 88, 90) a. What activities are in the critical path? How long is the project duration? b. If we want to crash the project for 2 months, what activities need to be crashed? How much additional cost required?Activity Normal_time Crash_time Normal_cost Crash_cost Slack A 31 17 4800 6200 В 14 14 5500 5500 C 34 18 5100 6600 21 17 4500 6800 E 15 15 5300 5300 F 17 17 5300 5300 The table shows normal time, crash time, normal cost, crash cost and slack time of activities in a project. According to this table which activity must be crashed first? Assume there is only one critical path. (Only type the name of the activity, Example: A. @orsdemir. Copyrighted content. Cannot be posted.) 0ㅇ11 2 0The following activities are part of a project to be scheduled using CPM: TIME (WEEKS) 7 6 ACTIVITY IMMEDIATE PREDECESSOR A BCDEFG O A-C-D-E-G O A-B-E-G O A-C-D-F-G O A-B-D-F-G AACB A Number of weeks A b. What is the critical path? B, D D E, F 24346 c. How many weeks will it take to complete the project?
- Table 3 gives time estimates in weeks for each activity (Durations are Time Expected obtained using PERT) Activity Preceded 1 Order review 2 Order vendor parts 3 Produce standard parts 4 Design custom parts Software development 5 6 Manufacture custom parts 7 Assemble 8 Test Duration 5 15 20 13 18 10 10 5 1 1 1 4 2,3,6 2,5 Resources Ryan Carly Ryan Lauren Connor Ryan Dawn Test Assuming that you have been engaged to programme the project activities indicated in Table 3 and Figure A8.1B (Air Control Project: Time Plan without Resources), USE CCPM (Critical Chain Project Management) to ESTIMATE the project duration by showing each and every stage of your programming process (indicate technical dependency with resources imposed).Title A small project has 12 activities – N, P, Q, R, S, T, U, V, W, X, Y and Z. The relationship among these activities and the duration of these activities are given in the Table. Activity Duration (in weeks) Depends upon N. Q 4 P. R Q S 8. R U R,S V 2 U W U T,V Y 1 W 3. X,Y The total float of the activity V' (in weeks, in 29jo integer) isPROJECT PLANNING & SCHEDULING WITH PERT/CPM Given the activities of a project; their optimistic (to), most likely (tm) and pessimistic (tp) time estimates (te); and their immediate predecessors shown below:1. When is the earliest project completion?2. Which activities are critical (should not be delayed)?3. Which activities are noncritical (can be delayed)?4. How long can each of the activities be delayed without delaying the wholeproject (maximum slack)? Activities ImmediatePredecessors Activity Times (to) Activity Times (tm) Activity Times (tp) Activity Times (te) Maximum Slack,months A - 1 4 13 B A 4 7 16 C A 2 2 2 D C 4 6 14 E - 1 3 5 F E 3 5 13 G - 7 10 13 H G 6 7 14 I B, D 1 1 1 J F, H, I 13 16 25
- Consider the following project activities with a normal unit: (The normal unit is Day) Activity Name Immediate Predecessor (list number/ name, separated by ‘,’) Normal Time A 6 B A 2 C A 4 D B, C 3 E D 1 F D 7 G E 4 H F, G 2 I F 6 J I 1 K H, J 5 Fill the following table: Activity Name Activity Time Earliest Expected Competition Time (TE) Latest Expected Competition Time (TL) Slack (TL-TE) A 6 B 2 C 4 D 3 E 1 F 7 G 4 H 2 I 6 J 1 K 5 Project Completion Time = Days The Critical Path is=Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: a. the critical activities for the leadership training program development project are: _____ b. the project length for the leadership training program development project= __ days. c. Slack time for each of the activities is: Activity: Slack time: A ______ B ______ C ______ D ______ E ______ F ______ G ______Given is a Project with network diagram and activity times as shown below. Activity Time (wks) A 13 B 5 Start с 14 A c) The Slack time of Activity C = Blank 3 weeks D D a) The Earliest Start (ES) time of Activity I = Blank 1 weeks 9 b) The Latest Start (LS) time of Activity B = Blank 2 weeks f) The Project Completion time = Blank 6 weeks d) The Earliest Finish (EF) time of Activity H = Blank 4 weeks e) The Latest Finish (LF) time of Activity B = Blank 5 weeks B F E 12 E F LL 17 H G 9 J H 15 - 15 J 2