A mass diagram from sta. 0+00 to sta. 50+00 is plotted as below. The free-haul distance is 1000'. The economical haul distance is 1500'. Both distances are marked in the diagram. Key station numbers are labeled. What's the free-haul volume from sta. 20 to sta. 50 in cubic yard? 1000 Cubic Yard 500 O -500 -1000 0+00 10+00 20+00 26+00 30+00 40+00 50+00 2+00 4+00 14+00 17+00 33+00 38+00 41+00 Stations 8+00 28+00
Q: town intends to dispose of its municipal solid waste in a 30-acre landfill that will be converted to…
A: What to find: Time taken to fill the landfill to the height of 6ft Given: Current population =…
Q: Structures, flexibillity method. I have been working on this and dont seem to be geeting it right,…
A: The beam is illustrated as: According to the Flexibility Method, the sum of all deflections due to…
Q: Question 1: Select an S shape for the tension member shown in Figure (1). The member shown will be…
A: Since the total design load (300 kips) is less than the nominal capacity (466.18 kips), the selected…
Q: Design the required rectangular sedimentation tank(s) for a water treatment plant given the…
A: Here is some information you can use, hope it can help you and God bless.
Q: H.W No.1: A pretension beam with variable eccentricity has a rectangular of 200 mm width and 500 mm…
A: Step 1: Step 2: Step 3: Step 4:
Q: A circular clarifier has diameter of 75 feet with an in-board launder (2 feet wide) set at 65 feet…
A: Step 1:Step 2:
Q: . Turk Telekom 3G 21:09 @%100 4 × CE272-9-conserv... Example 5.6 The velocity of the water leaving a…
A: Step 1: Step 2: Step 3: Step 4:
Q: The use of the following materials and explain their properties and Compositions: Polymers and…
A: Polymers are large molecules composed of repeated subunits known as monomers. They have a broad…
Q: For cross sectional areas shown, calculate the moment of inertia with respect to the horizontal x-x…
A:
Q: Refrigerant 134a expands in a piston-cylinder assembly from p₁ = 140 lb/in² and T₁ = 140°F to p₂ =…
A:
Q: Problem 2 If the ultimate Biochemical oxygen demand (BOD) for a wastewater sample is 200 mg/L and…
A: Step 1: Step 2: Step 3: Step 4:
Q: Water is being pumped at a steady rate of 500 gpm from a 12in diameter well. Thewell draws water…
A: Step 1: Given data. Step 2: Calculation for the Radius of influence. I hope it will help you please…
Q: 1. The lower ends of the three bars in the figure are at the same level before the uniform rigid…
A: Step 1: Step 2: Step 3: Step 4:
Q: Apply the following methods 1.) present worth method 2.) Annual worth method 3.) Benefit cost…
A: 1. Present Worth Method:• Calculate the future worth of the annual revenue using the given compound…
Q: ENVIRONMENTAL ENGINEERING a). List and describe the main features of the In-vessel Anaerobic…
A: a. In-vessel anaerobic digestion (IVAD) is a process that involves the breakdown of organic…
Q: 2. Solve the following problem Determine the maximum torque T that can be resisted by two shafts…
A:
Q: Stress in shaft due to Bending Load and Torsion. A shaft has a diameter of 4 cm. The cutting section…
A: First, we must identify the crucial point of the section where the combined effects of bending and…
Q: identify 3 research (published after 2010) on topics closely related to biological wastewater…
A: 2.Title: "Enhanced Biological Nutrient Removal in a Sequencing Batch Reactor Using…
Q: 3. Following information obtained from the Cooper's Town water reservoir. To complete a 100,000 m³/d…
A: Let's address each part of the question based on the provided water chemistry data from Cooper's…
Q: A gas undergoes a cycle in a piston-cylinder assembly consisting of the following three processes:…
A:
Q: Q4: A wastewater treatment plant as shown: The surface area of each unit 800 m². Depth of each unit…
A: Step 1: Analyse the question. Step 2: Approach question step by step. Step 3: Apply necessary…
Q: The beam AB supports two concentrated loads and rests on soil that exerts a linearly distributed…
A: Step 1:Step 2:Step 3:Step 4: Hope this helps!
Q: Determine the location of the centroid C (x, y) of the beam's cross-sectional area and then compute…
A:
Q: Assuming the start up flow for the clarifier is 1.7 mgd and the design peak hour flow is 5.2 mgd,…
A: Step 1: Step 2:Step 3:
Q: Which of the following statements apply (select all correct answers)? a)When the water table rises…
A: b) Design charts presented in the coursebook can be used to estimate the critical FoS associated…
Q: Your GIS team has provided the following flow direction and flow accumulation rasters to your…
A: Step 1: Step 2:
Q: Bar ABC has a rectangular cross section of 300mm by 100mm. Attached rod DB has a diameter of 20mm.…
A: Understanding the AC CircuitThe question likely involves an AC circuit containing an inductor (L)…
Q: Please solve all the questions asked
A: **Q3: Purposes**1. **Tie Bars**: In concrete pavements, tie bars serve as connectors between…
Q: The two-storey office building has a special reinforced concrete moment frame system.Design…
A: So, the design base shear is approximately 602.17 kN, the design lateral force for the 1st floor is…
Q: Your client has request that you design a cloth media disc filter for the tertiary filter in a new…
A: Step 1:Step 2: Step 3: Step 4:
Q: Determine the reactions at the beam supports for the given loading when M = 1515 N/m. The…
A: Step 1: Find the value of x. Step 2: Solve for the reaction and moment at B. I hope it will help you…
Q: The coefficients of friction between the block and the rail are Mg = 0.25 and Mk = 0.20. Given: P2 =…
A:
Q: ind the depth of trapezoidal channel of bed width 4m,bed slope of channel is 0.00059,and side slope…
A: The problem is asking us to find the depth of a trapezoidal channel given the bed width, bed slope,…
Q: Solve
A: The first part of the question is asking for the maximum moment developed in the beam. The maximum…
Q: 2. For an industrial wastewater activated sludge process, the amount of bsCOD in the influent…
A: Step 1: Step 2: Step 3: Step 4:
Q: A crane hoisting system has the following transfer function. 1 s4 +5s3+s² + 7s+ 11 Identify the…
A: Step 1: Step 2: Step 3: Step 4:
Q: Q1] If you know that the value of F=15 kN, N=50kN, what would be the resultant and the angle of…
A: STEP - 1:Given that,F=15kNN=50kNWe know that;STEP -2 :Resultant of friction of x and y component…
Q: = == 1 in.2, 10,000 lb. Each bar of the simple truss shown in Fig. 6.5a has cross-sectional area A;…
A: Step 1:Step 2:Step 3:Step 4:
Q: 6-Neglecting friction and the weights of the members, compute the magnitudes of the pin reactions at…
A:
Q: it a concrete encased steel composite column. It consists of a steel UC (universal column), with 8…
A: Step 1:Step 2:Step 3: Step 4:
Q: Irina finds an unlabeled box of fine needles and wants to determine how thick they are. A standard…
A: Step 1:Screen distance (D)=23.7 mDiameter of the central bright circle (d)=18.2 cm=0.182 mwavelength…
Q: ANALYSIS AND DESIGN OF DOUBLY REINFORCED CONCRETE BEAMS 1. A rectangular beam with a width of 350mm…
A: Solution: Analysis of doubly reinforced beam has the following scenarios 1. Both tension and…
Q: A concrete beam AB of span 15 m is post-tensioned by a cable which is concentric at supports A and B…
A:
Q: A 1000 MW pulverized coal fired steam plant (40% efficient) uses coal with a heat content of 11,250…
A: Part 1: Part 2: Part 3: Part 4:
Q: Can you please help me solve this homework question I am confused on the homework problem this is…
A: Step 1: Given,Structural number= SN=4 Single unit truck:Daily truck traffic= 13708000 lb single…
Q: Determine the surface dimensions and number of filters required to treat 23,000 m³/d if the rate of…
A: Step 1:Given: Flow rate to be treated = 23,000 m³/dMaximum filtration rate = 8 gpm/sfConvert the…
Q: 12.7 The lateral force that is generated during building shaking can be calculated with the…
A: 12.7. The lateral force generated during building shaking is proportional to the mass of the…
Q: solve all
A: If you have any queries please feel free to ask me.
Q: The beam AB has a negligible mass and thickness and is subjected to a force of 200 N. It is…
A:
Q: ENVIRONMENTAL ENGINEERING (Practice Questions) a). Define the Carbon Cycle and then explain the…
A: Detailed explanation: A. The carbon cycle is nature's way of reusing carbon atoms, which travel…
Please solve the problem and show your work how you got the answer pleas.
Step by step
Solved in 2 steps
- If the free haul area is between 4+30 and 14+30, what is the average haul distance (ft) for the net volume of material taken from the section between station 2+60 and 3+00? Response Feedback: The average distance between 2+60 and 3+00 is 20 ft. Add that to the distance from 3+00 to the free haul area, which begins at 4+30.Given the following Mass-Haul Diagram: Mass Diagram 5000 4000 3,500 3000 2,100 6.0 2,100 7.0 2000 8.0 1,500 1,500 g t--------- 6.0 8.0 O 1000 1,100 - 7.1 750 5.0 TO -1000 3-2000 -3000 -3,000 ´ -4000 -5000 5 10 15 20 25 Stations Limit of free haul = 600 ft Price of excavation = $3.50 Price of borrow = $3.75 Overhaul = $1.50 What is the total excavation cost to the nearest dollar? $30,000 O $28,000 $25,375 $20,250 O None of the above Net Cumulative YardageIn a site balancing project, the total haul distance starts from Sta. 2+720 and ends in Sta. 4+450. The freehaul distance starts 430 m. away from the starting station of the total haul distance and ends before the total haul distance which is also at a distance of 430 m. a. Get the total haul distance b. Locate the starting and end stations of the free haul distance c. Get the overhaul distance. d. Get the freehaul volume if it is estimated that the overhaul is approximately 5264 m3-m. . e. Sketch the mass diagram based on the given.
- The mass ordinates at the initial point ( sta 0+000) of a mass diagram is 50 cu m ,and at the last station (0+280) is - 200 cu m .If the length of economical haul is plotted horizontally to intersect the ( summit ) the mass diagram at a point having a mass ordinate of 120 cu m .The length of economical haul is 250 m long, compute the volume of borrowIf the free haul area is between 4+30 and 14+30, what is the average haul distance (ft) for the net volume of material taken from the section between station 2+60 and 3+00? 32Q1) For the following portion of mass haul diagram (each station is 50 m) answer the following questions: Station 4+00 7+00 6+00 5+00 3+00 2+00 1+00 0+00 -100 200 300 400 500 600 -700 -800 A) If the free haul distance =150 m, find the total cost within the free haul distance if the cost of excavation and transporting up to 150 m = 0.5 JD/ m? B) Find the limit of economical haul distance if the cost transporting is 0.1 JD/ m' for each 30 m beyond the first 150 m? C) Find the volume of waste and borrow materials? D) On the figure above specify the following: · Free haul distance and volume • Limit of economical haul distance and the overhaul volume • The waste and borrow material portion comulative volume m'
- 8-6. Determine the haul equation constants a and b for the following data. Average haul speed, mi/h Round-trip distance, mi/trip "Arip 4%-9 10 0.9 20 2.9 25 4.0 29 5.5 30 6.0 35 8.0 39 10.0 40 11.0 45 15.5 50 28.0The following net accumulations were calculated. The free haul area begins at station 4+30 and continues to 14+30. If the overhaul is charged at $10/yd³ station, what is the total overhaul cost ($)? Round to the nearest cent. from station to station net accumulation, yd³ 2+60 3+00 3.85 3+00 4+00 5.85 4+00 4+30 8.35 Response Feedback: 10x8.35x0.9281For the following mass haul diagram loop shown below, calculate the cost of earthwork, including excavation and hauling given that the cost of excavation is $2.0/m³ and the cost of overhaul is $0.150/m³.station. (Hint: Numbers shown on the loop are accumulative volumes (m³)) 1760 2150 2280 FHD = 200 m LEHD = 350 m
- Net Cumulative Yardage 5000 ● 4000 3000 2000 1000 -1000 -2000 -3000 -4000 -5000 None of these. 11.7 6.0 O 8.0 5.0 Given the Mass Haul Diagram above and the following information: Excavation Cost: $4.25/cu. yd. Borrow Cost: $4.50/cu. yd. Overhaul Cost: $0.75/sta*cu. yd. Free Haul Limit: 600 ft. Compute the limit of economic haul: O 12.0 -3,000 1,500 5 2,100 6.0 8.0 10 3,500 + 7.1 2,100 1,100 Stations 15 7.0 8.0 6.0 20 1,500 750 25ASAP PLS I RLLY NEED THIS IN 30 MINUTESIn a road construction, the lenght of economic haul was determine to be at station 100+111 whose area is17.01 square meters and station 100+428 whose area is 23.99 square meters. If the lenght of the free haul distance is 50m, determine the volume of the overhaul in cubic meters. Please take note that the distance from the balance station to both of the two stations are equal. Numerical answer only no units necessary.