You are charged with choosing a vendor to produce a new software that is going to benefit your company. The project has a life cycle of 8 years and MARR of 8% annual interest. Part a.) Draw the cash flow diagram for each vendor. Part b.) Calculate a PW cost for each vendor. Part c.) Indicate which vendor you would choose. Task Development Programming Operation Support Vendor M Cost, $ 200,000 150,000 42,000 20,000 40,000 30,000 Time Frame Now Years 1-4 Now Years 1-3 Years 1-8 Years 1-8 Vendor N Cost, $ 70,000 60,000 45,000 50,000 35,000 Time Frame Now Now Years 1-5 Years 1-8 Years 1-8 Vendor O Time Frame Cost, $ 150,000 Years 1-8

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter17: Long-term Investment Analysis
Section: Chapter Questions
Problem 10E
icon
Related questions
Question
You are charged with choosing a vendor to produce a new software that is going to benefit
your company. The project has a life cycle of 8 years and MARR of 8% annual interest.
Part a.) Draw the cash flow diagram for each vendor.
Part b.) Calculate a PW cost for each vendor.
Part c.) Indicate which vendor you would choose.
Task
Development
Programming
Operation
Support
Vendor M
Cost, $
200,000
150,000
42,000
20,000
40,000
30,000
Time
Frame
Now
Years 1-4
Now
Years 1-3
Years 1-8
Years 1-8
Vendor N
Cost, $ Time Frame
70,000
60,000
45,000
50,000
35,000
Now
Now
Years 1-5
Years 1-8
Years 1-8
Vendor O
Cost, $
150,000
Time Frame
Years 1-8
Transcribed Image Text:You are charged with choosing a vendor to produce a new software that is going to benefit your company. The project has a life cycle of 8 years and MARR of 8% annual interest. Part a.) Draw the cash flow diagram for each vendor. Part b.) Calculate a PW cost for each vendor. Part c.) Indicate which vendor you would choose. Task Development Programming Operation Support Vendor M Cost, $ 200,000 150,000 42,000 20,000 40,000 30,000 Time Frame Now Years 1-4 Now Years 1-3 Years 1-8 Years 1-8 Vendor N Cost, $ Time Frame 70,000 60,000 45,000 50,000 35,000 Now Now Years 1-5 Years 1-8 Years 1-8 Vendor O Cost, $ 150,000 Time Frame Years 1-8
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Knowledge Booster
Property Damage
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning