Which of the following statements is most correct? If a project’s internal rate of return (IRR) exceeds the cost of capital, then the project’s net present value (NPV) must be positive. If Project A has a higher IRR than Project B, then Project A must also have a higher NPV. The IRR calculation implicitly assumes that all cash flows are reinvested at a rate of return equal to the cost of capital. Answers a and c are correct. None of the answers above are correct.
Which of the following statements is most correct? If a project’s internal rate of return (IRR) exceeds the cost of capital, then the project’s net present value (NPV) must be positive. If Project A has a higher IRR than Project B, then Project A must also have a higher NPV. The IRR calculation implicitly assumes that all cash flows are reinvested at a rate of return equal to the cost of capital. Answers a and c are correct. None of the answers above are correct.
Chapter11: Cash Flow Estimation And Risk Analysis
Section11.1: Identifying Relevant Cash Flows
Problem 3ST
Related questions
Question
Which of the following statements is most correct?
- If a project’s
internal rate of return (IRR) exceeds the cost of capital, then the project’snet present value (NPV) must be positive. - If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.
- The IRR calculation implicitly assumes that all cash flows are reinvested at a rate of return equal to the cost of capital.
- Answers a and c are correct.
- None of the answers above are correct.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Recommended textbooks for you