The following graph represent different tasks that must be completed for a project.
The weights in the graph represent DAYS. What is the earliest day task 7 can begin?
5 days
3
3 days
2 days
6 days
8
1
2 days
3 days
3 days
6
4 deys
4
2 days
2 days 3 days
5
Answer and explain.
Transcribed Image Text:The following graph represent different tasks that must be completed for a project. The weights in the graph represent DAYS. What is the earliest day task 7 can begin? 5 days 3 3 days 2 days 6 days 8 1 2 days 3 days 3 days 6 4 deys 4 2 days 2 days 3 days 5 Answer and explain.
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Recommended textbooks for you
Glencoe Algebra 1, Student Edition, 9780079039897…
Glencoe Algebra 1, Student Edition, 9780079039897…
Algebra
ISBN:
9780079039897
Author:
Carter
Publisher:
McGraw Hill
Elementary Algebra
Elementary Algebra
Algebra
ISBN:
9780998625713
Author:
Lynn Marecek, MaryAnne Anthony-Smith
Publisher:
OpenStax - Rice University
Algebra: Structure And Method, Book 1
Algebra: Structure And Method, Book 1
Algebra
ISBN:
9780395977224
Author:
Richard G. Brown, Mary P. Dolciani, Robert H. Sorgenfrey, William L. Cole
Publisher:
McDougal Littell