Storm sewer system is to be provided to drain storm water to protect urban areas from flooding after episodes of rainfall. Storm sewer layout along with the contributing areas drained in specific sewer lines is shown in Figure A2= 26 ha C2=0.56 SS1 SS2 SS3 SS4 SS5 A2 = 16 ha C2=0.75 A6= 26 ha C6= 0.65 Sewer Name MH1 MH3 MH5 MH6 MH2 Main Sewer MH4 56 51 Length of Sewer (m) 51 66 61 A1= 11 ha C1= 0.60 A3= 26 ha C3= 0.70 A5= 31 ha C5= 0.70 Head of run MH1 MH2 MH3 MH1 MH4 MH5 MH2 MH3 MH4 MH5 1) Design the storm sewer system for "gravity flow" using the data given in Table Q1 assuming that the entry time to the pipe is the same for all sections and is equal to 6 min. All pipes are circular and made of concrete. All areas are in hectares. MH6 GE=142 m GE=140.9 m MH2 MH3 MH4 MH5 MH6 GE=140 m GE=139.1 m GE=138.2 m GE=137.0 m End of run

Solid Waste Engineering
3rd Edition
ISBN:9781305635203
Author:Worrell, William A.
Publisher:Worrell, William A.
Chapter8: Landfills
Section: Chapter Questions
Problem 8.9P
icon
Related questions
Question
Storm sewer system is to be provided to drain storm water to protect urban areas
from flooding after episodes of rainfall. Storm sewer layout along with the
contributing areas drained in specific sewer lines is shown in Figure
A2= 26 ha
C2=0.56
SS1
SS2
SS3
SS4
SS5
A2= 16 ha
C2=0.75
A6= 26 ha
C6= 0.65
Sewer Name
MH1
MH3
MH5
MH6
MH2
MH4
Main Sewer
56
51
51
66
61
Length of
Sewer (m)
A1= 11 ha
C1= 0.60
A3= 26 ha
C3= 0.70
A5= 31 ha
C5=0.70
Head of run
MH1
MH1
MH2
MH3
MH4
MH5
MH2
MH3
MH4
MH5
MH6
1) Design the storm sewer system for "gravity flow" using the data given in Table
Q1 assuming that the entry time to the pipe is the same for all sections and is
equal to 6 min. All pipes are circular and made of concrete. All areas are in
hectares.
GE=142 m
GE=140.9 m
MH2
MH3
MH4
MH5
MH6
GE=140 m
GE=139.1 m
GE=138.2 m
GE=137.0 m
End of run
2) Determine the invert elevations of the sewers assuming the minimum cover
criteria of 2 m and thickness of the pipe as 5 cm.
3) Use SWMM software to verify your results
Transcribed Image Text:Storm sewer system is to be provided to drain storm water to protect urban areas from flooding after episodes of rainfall. Storm sewer layout along with the contributing areas drained in specific sewer lines is shown in Figure A2= 26 ha C2=0.56 SS1 SS2 SS3 SS4 SS5 A2= 16 ha C2=0.75 A6= 26 ha C6= 0.65 Sewer Name MH1 MH3 MH5 MH6 MH2 MH4 Main Sewer 56 51 51 66 61 Length of Sewer (m) A1= 11 ha C1= 0.60 A3= 26 ha C3= 0.70 A5= 31 ha C5=0.70 Head of run MH1 MH1 MH2 MH3 MH4 MH5 MH2 MH3 MH4 MH5 MH6 1) Design the storm sewer system for "gravity flow" using the data given in Table Q1 assuming that the entry time to the pipe is the same for all sections and is equal to 6 min. All pipes are circular and made of concrete. All areas are in hectares. GE=142 m GE=140.9 m MH2 MH3 MH4 MH5 MH6 GE=140 m GE=139.1 m GE=138.2 m GE=137.0 m End of run 2) Determine the invert elevations of the sewers assuming the minimum cover criteria of 2 m and thickness of the pipe as 5 cm. 3) Use SWMM software to verify your results
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Drainage of pavements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Solid Waste Engineering
Solid Waste Engineering
Civil Engineering
ISBN:
9781305635203
Author:
Worrell, William A.
Publisher:
Cengage Learning,