Look at the cash flows for projects F and G given below. Cash Flows ($) NPV IRR at Project со F G C1 C2 C3 C4 (15,000) 7,200 7,200 7,200 0 20.7 2,905 (15,000) 3,600 3,600 3,600 3,600 3,600 3,600 3,600 3,600 17.3 4,206 C5 C6 C7 C8 (%) 10% 0 0 0 0 The cost of capital was assumed to be 10%. Assume that the forecasted cash flows for projects of this type are overstated by 7% on average. That is, the forecast for each cash flow from each project should be reduced by 7%. But a lazy financial manager, unwilling to take the time to argue with the projects' sponsors, instructs them to use a discount rate of 17%. a. What are the projects' true NPVs? (Do not round intermediate calculations. Round your answers to nearest dollar amount.) Project F Project G NPV at 10% b. What are the NPVs at the 17% discount rate? (Do not round intermediate calculations. Round your answers to nearest dollar amount.) Project F Project G NPV at 17%

Corporate Fin Focused Approach
5th Edition
ISBN:9781285660516
Author:EHRHARDT
Publisher:EHRHARDT
Chapter10: The Basics Of Capital Budgeting: Evaluating Cash Flows
Section10.4: Internal Rate Of Return (irr)
Problem 2ST
icon
Related questions
Question
Look at the cash flows for projects F and G given below.
Cash Flows ($)
NPV
IRR
at
Project
со
F
G
C1 C2 C3 C4
(15,000) 7,200 7,200 7,200 Ө
(15,000) 3,600 3,600 3,600 3,600 3,600 3,600 3,600 3,600 17.3 4,206
C5
C6
C7
Cg
(%) 10%
0
Ө
Ө
Ө
20.7 2,905
The cost of capital was assumed to be 10%. Assume that the forecasted cash flows for projects of this type are overstated by 7% on
average. That is, the forecast for each cash flow from each project should be reduced by 7%. But a lazy financial manager, unwilling to
take the time to argue with the projects' sponsors, instructs them to use a discount rate of 17%.
a. What are the projects' true NPVs? (Do not round intermediate calculations. Round your answers to nearest dollar amount.)
Project F
Project G
NPV at 10%
b. What are the NPVs at the 17% discount rate? (Do not round intermediate calculations. Round your answers to nearest dollar
amount.)
Project F
Project G
NPV at 17%
Transcribed Image Text:Look at the cash flows for projects F and G given below. Cash Flows ($) NPV IRR at Project со F G C1 C2 C3 C4 (15,000) 7,200 7,200 7,200 Ө (15,000) 3,600 3,600 3,600 3,600 3,600 3,600 3,600 3,600 17.3 4,206 C5 C6 C7 Cg (%) 10% 0 Ө Ө Ө 20.7 2,905 The cost of capital was assumed to be 10%. Assume that the forecasted cash flows for projects of this type are overstated by 7% on average. That is, the forecast for each cash flow from each project should be reduced by 7%. But a lazy financial manager, unwilling to take the time to argue with the projects' sponsors, instructs them to use a discount rate of 17%. a. What are the projects' true NPVs? (Do not round intermediate calculations. Round your answers to nearest dollar amount.) Project F Project G NPV at 10% b. What are the NPVs at the 17% discount rate? (Do not round intermediate calculations. Round your answers to nearest dollar amount.) Project F Project G NPV at 17%
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Knowledge Booster
Economic Value Added
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Corporate Fin Focused Approach
Corporate Fin Focused Approach
Finance
ISBN:
9781285660516
Author:
EHRHARDT
Publisher:
Cengage