Given the data for a project in table Q3, using the following 1. 8 hours as working day 2. The company will work all days. 3. Maximum number of workers available per day is 6 4. Activities cannot be break down 5. Budget will distributed equally per day, except for activities (B, H and L), the payment will be after two days of working: means that the first payment will be at the end of day2, then day four and so on. 6. They estimate that the work will starts on the first of November 2017 Develop a report containing the followings: 1. Date of finish GYSER 2. Early start and Slack time for each activity 3. Resource histogram 4. Cumulative Budget baseline curve 5. Interpret the final report

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
Given the data for a project in table Q3, using the following assumptions:
1.
8 hours as working day
2.
The company will work all days.
3.
Maximum number of workers available per day is 6
4.
Activities cannot be break down
5.
Budget will distributed equally per day, except for activities (B, H and L), the
payment will be after two days of working: means that the first payment will be
at the end of day2, then day four and so on.
6.
They estimate that the work will starts on the first of November 2017
Develop a report containing the followings:
Date of finish
BAD O GYEK
1.
2.
Early start and Slack time for each activity
3.
Resource histogram
4.
Cumulative Budget baseline curve
5.
Interpret the final report
co Table Q3
Duration (Hrs)
No of Workers
Budget
Activity
predecessor
A
None
48
12000
64
32000
C
16
10000
32
4.
12000
B,C
32
8000
B,C
16
6000
G
B,C
16
4
10000
H.
64
16000
3.
16
4000
32
1
12000
K
32
3
16000
H.
48
1
12000
Total Budget of
RM150000
Transcribed Image Text:Given the data for a project in table Q3, using the following assumptions: 1. 8 hours as working day 2. The company will work all days. 3. Maximum number of workers available per day is 6 4. Activities cannot be break down 5. Budget will distributed equally per day, except for activities (B, H and L), the payment will be after two days of working: means that the first payment will be at the end of day2, then day four and so on. 6. They estimate that the work will starts on the first of November 2017 Develop a report containing the followings: Date of finish BAD O GYEK 1. 2. Early start and Slack time for each activity 3. Resource histogram 4. Cumulative Budget baseline curve 5. Interpret the final report co Table Q3 Duration (Hrs) No of Workers Budget Activity predecessor A None 48 12000 64 32000 C 16 10000 32 4. 12000 B,C 32 8000 B,C 16 6000 G B,C 16 4 10000 H. 64 16000 3. 16 4000 32 1 12000 K 32 3 16000 H. 48 1 12000 Total Budget of RM150000
Expert Solution
steps

Step by step

Solved in 2 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,