Freeze Inc.’s CEO established as a goal for top management to complete the project on or before 22 weeks. What is the probability that this project will be completed on or before 22 weeks?
Q: ________ involves determining the functional relationship between variables, objective function, and...
A: Model construction is concerned with defining the functional connection between variables, objective...
Q: Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. ...
A: Given-
Q: Prepare a plan for Art Hill that gets the firm back on a coursetoward improved profitabili ty. Be su...
A: A Small Introduction about Aggregate Planning Aggregate planning is a strategy for fostering a ge...
Q: TRUE or FALSE 1. The value-based quality perspective is from the point view of the product design...
A: 1. Value-based quality perspective This quality viewpoint compares a product's quality to that of co...
Q: One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of ...
A: Develop a spreadsheet as shown below to get the desired answers.
Q: Explain the importance of “Increased levels of productivity ensuring successful lives” and make an e...
A: The accomplishment of higher productivity is one of the primary points of any business venture. High...
Q: Explain Briefly 1. Why is operations management is an important activity to a project? Who is suit...
A: Operations management is a field of business that deals include many different sub-fields for its wh...
Q: Question attahed in image
A: Note: - As we can answer only up to three subparts we will answer the first three(a, b, and c) subpa...
Q: "he percent change in productivity for one month last year versus one month this year on a multifact...
A:
Q: Explain the purpose of the project schedule.
A: A project schedule is like a time table for the project as it enables the project manager and whole ...
Q: Part 1 The accompanying dataset provides the closing prices for four stocks and the stock exchange o...
A: Given data for stock B is
Q: (H) linear programming formulation Let x- number of units i shipped to client j, using the indices f...
A: Given data is As the capacity was less than demand a dummy row is added.
Q: With the use of a diagram, show (illustrate) the typical levels of uncertainty or project risks asso...
A: A project risk is a dubious occasion that could conceivably happen during a project. In spite of our...
Q: please answer this for my review
A: Given that, Clients show up at a pace of one every moment. That is, 2 =1The server can deal with 0.4...
Q: What are the advantages and disadvantages or the shortestprocessing time (SPT) rule?
A: The shortest processing time often called the SPT technique can be stated as the technique that woul...
Q: Corry Corporation purchases 1,200,000 unit per year of one component. The Fixed Cost per order is $2...
A: given, purchases = 1,200,000 per year fixed cost = $25 carrying cost = 27% of its $2 cost
Q: Identify the kinds of research across fields.
A: Field research is a qualitative technique for research worried about comprehension and deciphering t...
Q: Edwarldo’s Manufacturing uses 2,400 units of a product per year on a continuous basis. The product C...
A: given, manufacturing = 2400 units carrying cost = $60 per year ordering cost = $250 safety stock = 8...
Q: 1,) In a community of 100,000 adults, subscribers to the newspaper, the Tallahassee Democrat, tend t...
A: Process analysis is a method that permits an unmistakable understanding of an organization's busines...
Q: Discuss any 4 principles of good product design. For each principle, identify a local example of a...
A: A Small Introduction about Product Design Product design is the interaction designers use to mix ...
Q: The marketing manager of a company that manufactures and distributes farming equipment (such as comb...
A: Adjusted seasonal index of autumn can be computed as below:
Q: 1. Using the appropriate control chart, determine two-sigma control limits for each case: a. An insp...
A: Given- The average no. of scratches C= 3.9 Lot Size = 100 mowers
Q: 5 project management groups have wide industry application in modern day project management. By usin...
A: practical example of project management 1. zippo- CHALLENGES: IMPROVE EFFICIENCY WHILE SCALING GLOB...
Q: A manager is quite concerned about the recent deterioration of a section of the roof on a building t...
A: The decision tree is a strong and well-known method for separating and foreseeing. A decision tree i...
Q: . Explain the importance of resource planning in project scheduling.
A: A resource plan is designed during the planning phase of any project. It is made by the person in c...
Q: b. What is the critical path? (You may select more than one answer. Single click the box with the qu...
A: Activity Immediate Predecessors Duration A - 3 B A 2 C A 4 D A 4 E B 6 F C,D 6 G D,F 2...
Q: Explain as brief and comprehensive why a new entrant would find it attractive to enter an industry. ...
A: Porter's five forces are described as the model that properly analyzes and identifies the competitiv...
Q: What are the problems faced by the avg production system in a developing country and what methods ar...
A: The major issue which the production system of a developing country faces are the efforts of the gov...
Q: What is Product Positioning, also explain how we can identify the possible competitive advantage in ...
A: Competitive advantage can be stated as the factors that permit an organization to generate or produc...
Q: Discuss any 4 principles of good product design. Quality, Utility/functionality, Asthically pleasing...
A: Product Design: The layout, blueprint or the outlook or any attribute either physically or virtually...
Q: An assembly line is to operate eight hours per day with a desired output of 200 units per day. The f...
A: Given-
Q: a. Find the critical path.
A: A network diagram is a visual representation of a project which identifying the activity relationshi...
Q: .•• 2.11 hired by a local restaurant to perform a factor-rating analysis to help the restaurant choo...
A: Outsourcing is the business practice of recruiting a party outside an organization to perform benefi...
Q: What is alternative optima in linear programming is about?
A: Linear method is described as the mathematical approach of determining the best possible solutions o...
Q: Discuss major risk management challenges. What function does risk management play in the development...
A: Risk management is tool which enables the firm to easily manage and control the risks associated wit...
Q: Explain the RBT
A: Resource based theory(ROT) is a theory which states the firm to in order to get strategic benefits o...
Q: ch, 1. Prepare a flowchart on preparing You need to follow the correct flow chart symbol. meal, you ...
A: COOKING AN EGG: 1. If Scrambled, then egg is cracked egg is broken with mike and butter ...
Q: Please read the case and answer the questions at the end. Please respond to two of your peers. Do yo...
A: 1. What makes the position of teaching assistant different from many jobs frequently represented by ...
Q: What are the key ideas in process analysis with multiple flow units?
A: The flow units which have more than one flow inputs are known as the multiple flow units. These proc...
Q: 55. The mail order firm of L. L. Pea receives an averageof 200 calls per hour, where times between c...
A: Given data is as follows: The arrival time is 200/hr. The service rate per hour is 20/hr. The wage r...
Q: Discussion Question #1- Using your "own words", discuss the differences among decision making under ...
A: Decision-making is the cycle of making decisions by recognizing a decision, gathering data, and eval...
Q: The Baton Rouge Police Department has five detectivesquads available for assignment to five open cri...
A: given,
Q: 5. Describe the three ways of achieving cost savings in industrial facilities.
A: Note: As per the Bartleby guidelines only the first three parts have been answered. For getting answ...
Q: Question CWD Oil produces two grades of gasoline: regular and premium. The profit contributions are...
A: Part (A): Decision Variables- Suppose-X= No. of gallons of regular gasoline to be producedY=No. of...
Q: plz solve both parts within 30-40 mins I'll give you multiple upvote
A: A Small Introduction about Productivity Productivity is the proficiency of the creation of labor ...
Q: A selection model that requires that a candidate has a minimum score level on all selection criteria...
A: The selection can be stated as the technique of selecting the right individual with the necessary sk...
Q: Use the following information to answer the questions below: TIMES (DAYS) PREDECESSOR JOB NO. JOB (S...
A: Forward Pass:Early Start (ES)= Maximum (or Highest) EF value from immediate Predecessor(s)Early Fini...
Q: CinEl is a motor company founded in 1937 with its headquarter in Barbados. CinEl is among the leadin...
A: Small Introduction about Production Management Production management is a course of organizing, ass...
Q: productivity in sales revenue/labor expense.
A: Labor productivity indicating the proportion between total output and total input cost. The calculat...
Q: Discuss significant risk management concerns. What role does risk management play in the creation of...
A: Risk management deals with protecting the company from all the possible threats, problems, and any o...
Need help solving C and D.
D) Freeze Inc.’s CEO established as a goal for top management to complete the project on or before 22 weeks. What
is the probability that this project will be completed on or before 22 weeks?
Step by step
Solved in 3 steps with 4 images
- The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Time (in weeks) Activity Description Immediate Predecessor Optimistic Most Probable Pessimistic A Meet with board ------ 1 1 2 B Hire coaches A 4 6 8 C Reserve pool A 2 4 6 D Announce Program B, C 1 2 3 E Meet with Coaches B 2 3 4 F Order Team Suits A 1 2 3 G Register Swimmers D 1 2 3 H Collect Fees G 1 2 3 I Plan first practice E, H, F 1 1 1 b) What is the project expected time? c) What is the probability of completing in 13 weeks? d) What is the…The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Time (in weeks) Activity Description Immediate Predecessor Optimistic Most Probable Pessimistic A Meet with board ------ 1 1 2 B Hire coaches A 4 6 8 C Reserve pool A 2 4 6 D Announce Program B, C 1 2 3 E Meet with Coaches B 2 3 4 F Order Team Suits A 1 2 3 G Register Swimmers D 1 2 3 H Collect Fees G 1 2 3 I Plan first practice E, H, F 1 1 1 a) What is the critical path? b) What is the project expected time? c) What is the probability of completing in 13…At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days). Immediate Most Activity Predecessor(s) Optimistic Probable Pessimistic A: Negotiate contract with - 10 11 12 selected musicians B: Reserve site - 8 10 12 C: Manage travel logistics A 2 7 9 for music group D: Screen & hire B 4 5 6 security personnel E: Arrange advertising C 7 7 7 & ticketing F: Hire parking staff A, D 8 9 16 G: Arrange concession sales E 6 7 11
- 8.35 Emerson Electric is considering the purchase of equipment that will allow the company to manufacture a new line of wireless devices for home appliance control. The first cost will be $80,000 and the life estimated is 6 years with a salvage value of $10,000. Three different salespeople have provided estimates regarding the added revenue the equipment will generate. Salespersons 1,2, and 3 have made estimates of $10,000, $16,000, and $18,000 per year, respectively. If the company's MARR is 8% per year, use a PW=based relation to perform a sensitivity analysis to assist in the decision to purchase the equipment. This question is in four parts. Part 4: Based on the results of the sensitivity analysis using three different salespeople's estimate of added revenue, what can you conclude about this purchase? The decision to purchase the equipment is sensitive to revenue estimates. Recommend the purchase of the equipment.. Do not recommend the purchase of the equipment..How Can You Get to a Backlog of over 100 Projects? There are never enough resources to get everything done." Backlogs build over time. Sacred cow projects get included in the selection system. Projects proposed from people who have left the airline stil reside in the project portfolio. Non-value-added projects somehow make their way into the project portfolio. Soon the queue gets longer. With everyone in IT working on too many projects concurrently, project completion and productivity are slow. Which Projects Remain? To cut the number of projects, the steering committee used a weighting scheme that reflected the airline's priorities, which were: fly safe, generate revenue, reduce costs, and customer service. The weighting scheme easily weeded out the fluff. Coady noted that "by the time you get to the 20s the margin of differentiation gets narrower and narrower." Of the remaining projects, project sponsors had to have solid justification why their project is important. Reduction of the…At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days). Immediate Most Activity Predecessor(s) Optimistic Probable Pessimistic A: Negotiate contract with - 10 11 12 selected musicians B: Reserve site - 8 10 12 C: Manage travel logistics A 2 7 9 for music group D: Screen & hire B 4 5 6 security personnel E: Arrange advertising C 7 7 7 & ticketing F: Hire parking staff A, D 8 9 16 G: Arrange concession sales E 6 7 11 Which project network is correct? IMG is attached Compute the expected duration and variance of each activity. If required, round your answer to two decimals. If your answer is zero, enter “0”.…
- 1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?The expected times and variances for the activities for a project for Test Marketers, Inc. are given below. (Assume time is provided in days.) ID 12345678 Description Pilot production Select channels of distrib. Develop mktg. program Test market Patent Full production Ad promotion Release Predecessor None None None 1 1 4 3 2,5,6,7 t₂ 6 7 4 4 10 16 3 2 Varlance [(b-a)/6]² 34225221 10V what is feasibility Report ?Define when and why we need it And also define who prepare this document.
- 3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: a) DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team. b) Find the critical path. c) What is the project completion time? • • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede: ACTIVITY DURATION (WEEKS) PRECEDES A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 — ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A — 2 B — 5 C — 1 D B…Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow. Time Estimates (In weeks) Optimistic(a) Most Activity Immediate predecessor(s) Pessimistic likely(b) | (m) A 4 8. 10 В A 8. 24 C A 8. 12 16 D A 4 6. 10 E B 1 2 3 F E,C 8. 20 G E,C F 3 4 2 2 F 6. 6. 6. J D,J,H 4 6. 12 K I,J 2 3 1. What is the expected (estimated) time for each activity? 2. Based on the calculation of estimated times, what is the critical path? 3. What is the estimated time of the critical path? 4. What is the activity variance along the critical path? 5. What is the probability of completion of the project before a week 46?Gabrielle Foley, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern is the hiring of a manager and several associates who are animal lovers. She also has to coordinate the renovation of a building that was previously owned by a chic clothing store. Foley has gathered the data shown in the table below. Activity A B с D E F G H Description Interview for new manager Renovate building Place ad for associates and interview applicants Have new manager prospects visit Purchase equipment for new store and install Check employee applicant references and make final selection Check references for new manager and make final selection Hold orientation meetings and do payroll paperwork Immediate Predecessor(s) III A CDL А B с E, F, G Time (weeks) a 1 752261 m b 29655 2 7 2 3 7348234 17 13 6 12 14 a. How long is the project expected to take? The project is expected to take 18 weeks. (Enter your response as a whole number.) b. Suppose that Foley has a personal goal of…