Curtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod Associates on July 1, 2024, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,060,000. The building was completed on December 31, 2026. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date Required: At 12-31-2024 10% $ 360,000 3,240,000 721,000 At 12-31-2025 $ 2,562,000 1,708,000 2,190,000 At 12-31-2026 60% 100% $ 4,321,000 0 4,060,000 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2024 and 2025 as either cost in excess of billings or billings in excess of costs. Complete this question by entering your answers in the tabs below. Req 1 and 2 Req 3 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. Note: Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign. Req 1 Show less A Req 2 Year Gross Profit (Loss) Recognized ("Upon Completion") Gross Profit (Loss) Recognized ("Over Time") 2024 2025 2026 Total project profit (loss) $ < Req 1 and 2 0 $ Req 3 > 0
Curtiss Construction Company, Incorporated, entered into a fixed-price contract with Axelrod Associates on July 1, 2024, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,060,000. The building was completed on December 31, 2026. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the contract were as follows: Percentage of completion Costs incurred to date Estimated costs to complete Billings to Axelrod, to date Required: At 12-31-2024 10% $ 360,000 3,240,000 721,000 At 12-31-2025 $ 2,562,000 1,708,000 2,190,000 At 12-31-2026 60% 100% $ 4,321,000 0 4,060,000 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. 3. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute the amount to be shown in the balance sheet at the end of 2024 and 2025 as either cost in excess of billings or billings in excess of costs. Complete this question by entering your answers in the tabs below. Req 1 and 2 Req 3 1. Compute gross profit or loss to be recognized as a result of this contract for each of the three years. Curtiss concludes that the contract does not qualify for revenue recognition over time. 2. Assuming Curtiss recognizes revenue over time according to percentage of completion, compute gross profit or loss to be recognized in each of the three years. Note: Leave no cells blank - be certain to enter "0" wherever required. Loss amounts should be indicated with a minus sign. Req 1 Show less A Req 2 Year Gross Profit (Loss) Recognized ("Upon Completion") Gross Profit (Loss) Recognized ("Over Time") 2024 2025 2026 Total project profit (loss) $ < Req 1 and 2 0 $ Req 3 > 0
Chapter16: Accounting Periods And Methods
Section: Chapter Questions
Problem 41P
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Recommended textbooks for you
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning