Consider the following simplified production process for an electronic device. Demand = 50,000 devices/Year Price = $50 each Raw Material = $5/device Employee Wage = $25/hr Number of Employees = 5 (1/workstation) Each Employee Works 2,080 hrs/year (40 hrs/week, 52 weeks/year) Other Expenses = $1,500,000/Year Color of the device: Green Workstation Processing Time 7 minutes 1 10 minutes 4 minutes 4 5 minutes 1 minute An Engineer proposes buying a new fixture to reduce total processing time by 4 minutes. The new fixture, which will cost $1,000, would allow some work to be transferred from workstation 100 to 200. Assume 2 minutes of work will be transferred from 1 to 2 and processing time of 1 will go down to 5 minutes, processing time of 4 will go down to 3 minutes and processing time of 2 will go up to 12 minutes. Would you approve this change? Explain Why? State your assumptions and show your math. 2. 3.

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter2: Basic Cost Management Concepts
Section: Chapter Questions
Problem 8CE: Jean and Tom Perritz own and manage Happy Home Helpers, Inc. (HHH), a house-cleaning service. Each...
icon
Related questions
Question
Sir please help me urgently please provide a complete answer
Consider the following simplified production process
for an electronic device.
Demand = 50,000 devices/Year
Price = $50 each
Raw Material = $5/device
Employee Wage = $25/hr
Number of Employees = 5 (1/workstation)
Each Employee Works 2,080 hrs/year (40 hrs/week,
52 weeks/year)
Other Expenses = $1,500,000/Year
Color of the device: Green
Workstation
Processing Time
7 minutes
1
10 minutes
3
4 minutes
5 minutes
1 minute
An Engineer proposes buying a new fixture to
reduce total processing time by 4 minutes. The new
fixture, which will cost $1,000, would allow some
work to be transferred from workstation 100 to 200.
Assume 2 minutes of work will be transferred from 1
to 2 and processing time of 1 will go down to 5
minutes, processing time of 4 will go down to 3
minutes and processing time of 2 will go up to 12
minutes. Would you approve this change? Explain
Why? State your assumptions and show your math.
Transcribed Image Text:Consider the following simplified production process for an electronic device. Demand = 50,000 devices/Year Price = $50 each Raw Material = $5/device Employee Wage = $25/hr Number of Employees = 5 (1/workstation) Each Employee Works 2,080 hrs/year (40 hrs/week, 52 weeks/year) Other Expenses = $1,500,000/Year Color of the device: Green Workstation Processing Time 7 minutes 1 10 minutes 3 4 minutes 5 minutes 1 minute An Engineer proposes buying a new fixture to reduce total processing time by 4 minutes. The new fixture, which will cost $1,000, would allow some work to be transferred from workstation 100 to 200. Assume 2 minutes of work will be transferred from 1 to 2 and processing time of 1 will go down to 5 minutes, processing time of 4 will go down to 3 minutes and processing time of 2 will go up to 12 minutes. Would you approve this change? Explain Why? State your assumptions and show your math.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Market Efficiency
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College