Case study 01 - Inventory Management You are the accounting officer of Zhaka CC, a small construction firm. The members are concerned about their inventory management, where up until now, ordering of raw materials has been haphazard and largely by guesswork. The members of Zhaka CC are anticipating an upsurge in demand for their services. They realise that they need to manage their inventory effectively if they want to be a successful player in the building industry. They have asked you to look at their anticipated brick consumption and make appropriate recommendations. The followingdata is relevant:– Budgeted consumption  maximum 300 000 bricks/month  minimum 100 000 bricks/month  average 200 000 bricks/month  annual 2 400 000 bricks/year Additional information: Lead time for delivery from the brick manufacturer, Kwasi Ltd, is a maximum of two months, a minimum of two weeks, and an average of one month. Price per brick is R2. Holding cost is 10% of stock value. Ordering cost is R1 500 per order. Required:  Determine when businesses might maintain high or low inventory levels and also how to determine their ideal inventory levels

Principles of Cost Accounting
17th Edition
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Edward J. Vanderbeck, Maria R. Mitchell
Chapter2: Accounting For Materials
Section: Chapter Questions
Problem 2MC
icon
Related questions
Question
100%

Case study 01 - Inventory Management
You are the accounting officer of Zhaka CC, a small construction firm. The members are concerned about their inventory management, where up until now, ordering of raw materials has been haphazard and largely by guesswork. The members of Zhaka CC are anticipating an upsurge in demand for their services. They realise that they need to manage their inventory effectively if they want to be a successful player in the building industry.
They have asked you to look at their anticipated brick consumption and make appropriate recommendations. The followingdata is relevant:– Budgeted consumption

 maximum 300 000 bricks/month
 minimum 100 000 bricks/month
 average 200 000 bricks/month
 annual 2 400 000 bricks/year
Additional information:
Lead time for delivery from the brick manufacturer, Kwasi Ltd, is a maximum of two months, a minimum of two weeks, and an average of one month.
Price per brick is R2.
Holding cost is 10% of stock value.
Ordering cost is R1 500 per order.

Required:  Determine when businesses might maintain high or low inventory levels and also how to determine their ideal inventory levels

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning
Excel Applications for Accounting Principles
Excel Applications for Accounting Principles
Accounting
ISBN:
9781111581565
Author:
Gaylord N. Smith
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Survey of Accounting (Accounting I)
Survey of Accounting (Accounting I)
Accounting
ISBN:
9781305961883
Author:
Carl Warren
Publisher:
Cengage Learning
Century 21 Accounting General Journal
Century 21 Accounting General Journal
Accounting
ISBN:
9781337680059
Author:
Gilbertson
Publisher:
Cengage
Century 21 Accounting Multicolumn Journal
Century 21 Accounting Multicolumn Journal
Accounting
ISBN:
9781337679503
Author:
Gilbertson
Publisher:
Cengage