"Blast it!" sald David Wilson, president of Teledex Company. "We've Just lost the bid on the Koopers Job by $2,000. It seems we're either too high to get the Job or too low to make any money on half the Jobs we bid." Teledex Company manufactures products to customers' specifications and uses a Job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply Its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year. Department Fabricating Machining $ 358,750 $ 410,000 $ 92,25e s 861,000 $ 25,e00 $ 182,500 $ 307,500 $ 615,000 ASsembly Total Plant Manufacturing overhead Direct labor Jobs require varylng amounts of work In the three departments. The Koopers Job, for example, would have required manufacturing costs In the three departments as follows: Fabricating $ 3,500 $ 3,80e Department Machining $ 200 $ 5ee Assembly Total Plant $ 5,600 $11, eee Direct materials $1,900 $ 6,700 Direct labor Manufacturing overhead Requlred: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers Job. 2. Suppose that Instead of using a plantwlide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been appled to the Koopers Job. 4. Assume that it is customary In the Industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). a. What was the company's bid price on the Koopers Job using a plantwide predetermined overhead rate? b. What would the bid price have been If departmental predetermined overhead rates had been used to apply overhead cost?

Excel Applications for Accounting Principles
4th Edition
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Gaylord N. Smith
Chapter17: Job Order Costing (job)
Section: Chapter Questions
Problem 7R: Nutts management is very concerned about the cost of overhead on its jobs. When jobs are complete,...
icon
Related questions
Question
"Blast It!" sald David Wilson, president of Teledex Company. "We've Just lost the bid on the Koopers job by $2,000. It seems we're
either too high to get the job or too low to make any money on half the Jobs we bid."
Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a
plantwide predetermined overhead rate based on direct labor cost to apply Its manufacturing overhead (assumed to be all fixed) to
Jobs. The following estimates were made at the beginning of the year.
Department
Fabricating Machining
Assembly
Total Plant
$ 410,e00
Manufacturing overhead
Direct labor
24
358,750
24
92,250
861,e0e
24
205, 000
$ 102,500
$ 307,500
%24
615,e00
Jobs require varying amounts of work In the three departments. The Koopers Job, for example, would have requlred manufacturing
costs in the three departments as follows:
Fabricating
$ 3,500
$ 3,800
Department
Machining
$ 200
$ 5ee
Assembly
$ 1,900
$ 6,700
Total Plant
$ 5,600
$11,000
Direct materials
Direct labor
Manufacturing overhead
Required:
1. Using the company's plantwide approach:
a. Compute the plantwide predetermined rate for the current year.
b. Determine the amount of manufacturing overhead cost that would have been appled to the Koopers Job.
2. Suppose that Instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined
overhead rates based on direct labor cost. Under these conditions:
a. Compute the predetermined overhead rate for each department for the current year.
b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers Job.
4. Assume that It is customary in the Industry to bid jobs at 150% of total manufacturing cost (direct materlals, direct labor, and applied
overhead).
a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate?
b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?
Complete this question by entering your answers in the tabs below.
Required 1A
Required 1B
Required 2A
Required 28
Required 4A
Required 48
Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined
overhead rates based on direct labor cost. Determine the amount of manufacturing overhead cost that would have been
applied to the Koopers job.
Manufacturing overhead cost applied
< Required 2A
Required 4A >
Transcribed Image Text:"Blast It!" sald David Wilson, president of Teledex Company. "We've Just lost the bid on the Koopers job by $2,000. It seems we're either too high to get the job or too low to make any money on half the Jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply Its manufacturing overhead (assumed to be all fixed) to Jobs. The following estimates were made at the beginning of the year. Department Fabricating Machining Assembly Total Plant $ 410,e00 Manufacturing overhead Direct labor 24 358,750 24 92,250 861,e0e 24 205, 000 $ 102,500 $ 307,500 %24 615,e00 Jobs require varying amounts of work In the three departments. The Koopers Job, for example, would have requlred manufacturing costs in the three departments as follows: Fabricating $ 3,500 $ 3,800 Department Machining $ 200 $ 5ee Assembly $ 1,900 $ 6,700 Total Plant $ 5,600 $11,000 Direct materials Direct labor Manufacturing overhead Required: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been appled to the Koopers Job. 2. Suppose that Instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers Job. 4. Assume that It is customary in the Industry to bid jobs at 150% of total manufacturing cost (direct materlals, direct labor, and applied overhead). a. What was the company's bid price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 1B Required 2A Required 28 Required 4A Required 48 Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. Manufacturing overhead cost applied < Required 2A Required 4A >
"Blast it!" sald David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers Job by $2,000. It seems we're
elther too high to get the Job or too low to make any money on half the Jobs we bid."
Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a
plantwide predetermined overhead rate based on direct labor cost to apply Its manufacturing overhead (assumed to be all fixed) to
Jobs. The following estimates were made at the beginning of the year.
Department
Fabricating Machining
$ 358,750 $ 410, e00
$ 102,500
Assembly
92, 250
$ 307,500 S
Total Plant
Manufacturing overhead
Direct labor
861,e0e
615, eee
24
205,000
Jobs require varyIng amounts of work In the three departments. The Koopers job, for example, would have requlred manufacturing
costs In the three departments as follows:
Fabricating
$ 3,500
$ 3,800
Department
Machining
$ 200
$ 500
Assembly
$1,900
$ 6,700
Total Plant
$ 5,600
$11,000
Direct materials
Direct labor
Manufacturing overhead
Requlred:
1. Using the company's plantwide approach:
a. Compute the plantwide predetermined rate for the current year.
b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.
2. Suppose that Instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined
overhead rates based on direct labor cost. Under these conditions:
a. Compute the predetermined overhead rate for each department for the current year.
b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers Job.
4. Assume that It is customary In the Industry to bid jobs at 150% of total manufacturing cost (direct materlals, direct labor, and applied
overhead).
a. What was the company's bld price on the Koopers job using a plantwide predetermined overhead rate?
b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?
Complete this question by entering your answers in the tabs below.
Required 1A
Required 18
Required 2A
Required 28
Required 4A
Required 48
Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined
overhead rates based on direct labor cost. Compute the predetermined overhead rate for each department for the current
year.
Predetermined Overhead Rate
Fabricating department
Machining department
of direct labor cost
%
%
of direct labor cost
Assembly department
%
of direct labor cost
Transcribed Image Text:"Blast it!" sald David Wilson, president of Teledex Company. "We've just lost the bid on the Koopers Job by $2,000. It seems we're elther too high to get the Job or too low to make any money on half the Jobs we bid." Teledex Company manufactures products to customers' specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply Its manufacturing overhead (assumed to be all fixed) to Jobs. The following estimates were made at the beginning of the year. Department Fabricating Machining $ 358,750 $ 410, e00 $ 102,500 Assembly 92, 250 $ 307,500 S Total Plant Manufacturing overhead Direct labor 861,e0e 615, eee 24 205,000 Jobs require varyIng amounts of work In the three departments. The Koopers job, for example, would have requlred manufacturing costs In the three departments as follows: Fabricating $ 3,500 $ 3,800 Department Machining $ 200 $ 500 Assembly $1,900 $ 6,700 Total Plant $ 5,600 $11,000 Direct materials Direct labor Manufacturing overhead Requlred: 1. Using the company's plantwide approach: a. Compute the plantwide predetermined rate for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job. 2. Suppose that Instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions: a. Compute the predetermined overhead rate for each department for the current year. b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers Job. 4. Assume that It is customary In the Industry to bid jobs at 150% of total manufacturing cost (direct materlals, direct labor, and applied overhead). a. What was the company's bld price on the Koopers job using a plantwide predetermined overhead rate? b. What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost? Complete this question by entering your answers in the tabs below. Required 1A Required 18 Required 2A Required 28 Required 4A Required 48 Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Compute the predetermined overhead rate for each department for the current year. Predetermined Overhead Rate Fabricating department Machining department of direct labor cost % % of direct labor cost Assembly department % of direct labor cost
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Pricing Decisions
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Excel Applications for Accounting Principles
Excel Applications for Accounting Principles
Accounting
ISBN:
9781111581565
Author:
Gaylord N. Smith
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College