b. What is the critical path? ⒸA-C-F-H OA-D-F-H OA-D-G-H OB-E-G-H

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
The following represents a project that should be scheduled using CPM:
IMMEDIATE
ACTIVITY PREDECESSORS
A
B
C
D
E
G
H
A
A
B
C, D
D, E
F, G
b. What is the critical path?
ⒸA-C-F-H
OA-D-F-H
OA-D-G-H
OBE-GH
TIMES (DAYS)
a
1
1.
H.N
2
3
3
1
2
EMNNms
3
2
3
2 3
4
4
4
4
S
b
4
6533
EU
11
5
65
Transcribed Image Text:The following represents a project that should be scheduled using CPM: IMMEDIATE ACTIVITY PREDECESSORS A B C D E G H A A B C, D D, E F, G b. What is the critical path? ⒸA-C-F-H OA-D-F-H OA-D-G-H OBE-GH TIMES (DAYS) a 1 1. H.N 2 3 3 1 2 EMNNms 3 2 3 2 3 4 4 4 4 S b 4 6533 EU 11 5 65
c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 2 decimal places.)
Project completion time
d. What is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability
for your computed Z-value. Do not round intermediate calculations. Round "2" value to 2 decimal places and final answer to 4
decimal places.)
Probability
10 00 days
09994
Transcribed Image Text:c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Project completion time d. What is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "2" value to 2 decimal places and final answer to 4 decimal places.) Probability 10 00 days 09994
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 9 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.