At a border inspection station, vehicles arrive at the rate of 10 per hour in a Poisson distribution. For simplicity in this problem, assume there is only one lane and one inspector, who can inspect vehicles at the rate of 12 per hour in an exponentially distributed fashion. a. What is the average length of the waiting line? (Round your answer to 2 decimal places.) Average length Answer is complete and correct. 4.17 customers b. What is the average time that a vehicle must wait to get through the system? Average time Answer is complete and correct. 30 minutes
Q: An Assembly line with 17 tasks is to be balanced. The longest task is 2.2 minutes, and the total…
A: An assembly line indicating the task allocation to the workstation based on different heuristics.…
Q: Portfolio Management If x dollars are invested in a company that controls, say, 30% of the market…
A:
Q: Use the following information in a table, about the activities of a project of a textile factory,…
A: Given information is
Q: The owner of Crackers, Inc. produces both Deluxe (D) and Classic (C) crackers. She only has 4,800…
A: Decision variables: Suppose-D be the no. of boxes of deluxe crackersC be the no. of boxes of…
Q: Borges Machine Shop, Inc., has a 1-year contract for the production of 75,000 gear housings for a…
A: Given table; Particulars GPE FMS DM Units 75000 75000 75000 Fixed Cost 100000 225000…
Q: Minimum number of unlading facilities. Probability (each unloading facility is busy) Probability…
A: NOTE: We are allowed to do the first three sub-parts only. The queuing theory was first developed in…
Q: Operations Management CH 7 Question 7 The Bijou Theater shows vintage movies. Customers arrive at…
A: Given data: Arrival rate (λ) = 80 per hour Service rate(µ) = =3600 seconds 40 seconds/customer =…
Q: A stock item has a count of 792 units, a cost of R3 and carrying charge of 20%. If the item is used…
A: Given: On- hand inventory = 792 usage per day = 36
Q: M-Method. Consider the following set of constraints: -2x1 + 3x2 = 3 (1) 4x1 + 5x2 >10 (2) X1 + 2x2 <…
A: (a)
Q: What is the economic order quantity? The EOQ is ______ units (round your response to the nearest…
A: Economic order quantity is a measurement of the number of units needed to fulfill the customer’s…
Q: Find attached the scenario - Discuss possible ways that Checkers can utilise evaluate and select a…
A: Suppliers are one of the core elements of a business. They are the driving force for any business…
Q: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine.…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Environmental Impact Assessment vs. Strategic Environmental Assessment and Management, Post-Project…
A: There are certain environmental assessments that are performed before a project is planned and…
Q: Maximize C- SM 11N subject to 4M + 6N s 13 7M+ 4N ≤ 13 and M20, N2₂0. What is the optimal value of…
A: Linear programming is a mathematical method for determining a way to achieve the best outcome for a…
Q: What is the Simple Exponential Smoothing forecast for September if we use alpha smoothing constant…
A: Simple exponential Smoothing is time series forecasting method. It is calculated with following…
Q: What types of scheduling decisions are management likely to encounter in the following operations?…
A: The purpose of scheduling is to meet both efficiency and customer service objectives by ensuring…
Q: Procurement is just like plants and animals, it’s born, it grows, it matures and eventually dies’.…
A: The process and methods involved in purchasing or obtaining any material, good or thing that a…
Q: Solve the following linear program by the solver method
A: Linear Programming is a statistical and mathematical technique used in operations management.…
Q: Your firm received an RFP (request for proposal) on a wire harness from GM with fixed costs of $1…
A: A break-even price is the value change that just recovers one's initial cost or investment. The…
Q: 2. A distillery makes three kinds of authentic Philippine wine: Sweet, Regular, and Extra Dry. The…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Explain the role of transportation in logistics. Support your answer with an example ?
A: Logistics is the science and art of organising the smooth transport of goods, data, and other…
Q: analyse the role of operations management capacity planning and control in a clothing business and…
A: Operations management is the process of designing, implementing, and controlling the production and…
Q: Summary of this case study, and the recommendation for this case study
A: The company was started when the owner was studying and the company earned high revenue ($100,000)…
Q: Construct a decision tree of the above situation clearly identifying the decision and chance nodes.l…
A: Decision trees are commonly used to predict the expected payoff for a decision. The expected payoff…
Q: Answer the following questions based on the Strategy Region graph given below. The objective is to…
A: The expected value of a decision is the sum of all possible values, weighted by the probability of…
Q: Which of the following could not be a constraint for a linear programming problem? Multiple Choice…
A: Constraints assist to bind a parameter & variable with upper & lower limitations. Variable…
Q: a) Using a 2-year moving average, the forecast for year 6 = number). miles (round your response to…
A: Moving averages are a type of average that is computed by taking the average of a set of…
Q: Which of the following statements is NOT true? O A feasible solution satisfies all constraints. An…
A: Feasible solution in linear programming problem indicating the region which satisfy all constrain…
Q: The chart below is given to highlight on the process of Operations Management. Accordingly answer…
A: Here, I have been given a chart where we could see that inputs are fed through the production…
Q: List out the benefits of biometric authentication?
A: Ans) Biometric authentication as the name suggests it is the process of authenticating each and…
Q: Suppose the optimistic estimate for completing a particular task is 2 weeks, the pessimistic…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: I need help with the multifactor productivity formula Facility processed 240 orders per hour…
A: Multifactor productivity is a theory that studies the relationship between the factors of…
Q: For a inear programming problem with constraint 22*x + 17 "y <= 1082 if the optimal solution is x =…
A: Linear programming is a mathematical technique that can be used to optimize a decision-making…
Q: To monitor the number of blemishes on a polished surface a company randomly selects 10 units of…
A: C-chart is a model of control chart which identifying the controllability based on counted type of…
Q: 1. Trojan Pizza shop has three workers and two stoves. Whenever the workers are idle, the shop…
A: Capacity of any process is defined by the capacity of its bottleneck workstation. Bottleneck…
Q: WEEK 1 maner 234567 ∞ 8 FORECAST DEMAND 135 135 135 134 134 144 155 156 Week 1 2 3 4 5 6 7 8 ACTUAL…
A: MAD is the proportion between total absolute error values and the number of weeks considered to…
Q: D 2 Dave's earliest start (ES) and earliest finish (EF) are:
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: 1. Inventory Problem Figure 6 shows the inventory levels of dried Rainier cherries at a natural food…
A: Given data is Annual demand (D) = 800 Ordering cost (S) = $16 Carrying cost (C) = $4
Q: SOLVE THE FOLLOWING USING EXCEL 8. A manager is trying to decide whether to purchase a certain part…
A: Total cost = fixed cost + (variable cost per unit X total units)
Q: i cant find the answer for societal supply chain management
A: The green supply chain is simply a supply chain that focuses on protecting the environment or at…
Q: Step 1 of 4: Determine the three-period moving average for the next time period. If necessary, round…
A: Forecasting is a technique used to predict future outcomes on the basis of past data. In businesses…
Q: IN THE MID-1960S, WALT DISNEY'S DREAM was to build a family resort destination like no other. The…
A: Note: - Since the exact question that has to be answered is not specified we will answer the first…
Q: Develop a project network for this problem. b) Determine the EST, EFT, LST, LFT, and slack for each…
A: The critical path is the most important task that needs to be completed first before the project can…
Q: a) Activity that should be crashed first to reduce the project duration by 1 day is A b) Activity…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: The Brew House needs to decide which of two coffee maker designs is better environmentally. Using…
A: We know that, Revenue retrieval = Total of Resale revenue + Total of recycling revenue - Total of…
Q: So how to calculate the following below: Avg. lateness = ? days Avg. completion time = ?? days…
A: Given data:
Q: (a) Formulate a 0-1 integer linear programming model that will enable Bayside's management to…
A: (a) Minimize Z = 1x1 + 1x2 + 1x3 + 1x4 + 1x5 + 1x6 + 1x7 + 1x8 + 1x9 + 1x10 + 1x11 + 1x12 + 1x13…
Q: Discussion Questions* 1. Name and justify several factors that Hoffman could use in forecasting…
A: Forecasting – Several Factors: As per the given case, Hoffman can use the following…
Q: Explain the key aspects of operation management decision making
A: According to the business definition, operations management is the design, execution, and control of…
Q: General Appliance Corporation (GAC) produces refrigerators at three plants: Akron, Evansville, and…
A: Transportation problem is a special case of asignment problem covered in Linear programming…
I need assitance with solving this problem 3. I made numerous attempts to solve. however I am still having issues. Please provide a step by step explanation so, I can use it as notes for future reference. Respectfully thank you
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images
- 1.) What is not considered a measure of system performance in a queuing analysis? average number waiting in line service time system utilization average number in the system 2.) Which of the following is true of a customer who reneges? after joining the queue, becomes impatient and leaves tries to get through as quickly as possible by moving from queue to queue never returns after going through the queue refuses to join the queue because it is too longIn queuing system 1.- What is the average Queue lenght ? What is the expected waiting time ? 2.-13. Suppose AirOM passengers arrive to the check-in desk every 100 seconds (on average). The desk is staffed by a single ticketing agent, who takes 1.4 minutes (on average) to process a passenger. The arrivals follow a Poisson process and the service time is distributed exponentially. What is a passenger’s average waiting time (in seconds)? Enter a single number as your answer. If your final number is not integer, keep two decimal places in your answer.
- In a waiting line situation, arrivals occur at a rate of 2 per minute, and the service times average 18 seconds. Assume the Poisson and exponential distributions. a. What is λ? b. What is μ? c. Find probability of no units in the system. d. Find average number of units in the system. e. Find average time in the waiting line. f. Find average time in the system. g. Find probability that there is one person waiting. h. Find probability an arrival will have to wait. Please show a corrct solution and answer. Thank you.At a border inspection station, vehicles arrive at the rate of 8 per hour in a Poisson distribution. For simplicity in this problem, assume that there is only one lane and one inspector, who can inspect vehicles at the rate of 15 per hour in an exponentially distributed fashion. a. What is the average length of the waiting line? (Round your answer to 2 decimal places.) b. What is the average time that a vehicle must wait to get through the system? (Round your answer to 2 decimal places.) c. What is the utilization of the inspector? (Round your answer to 1 decimal place.) d. What is the probability that when you arrive there will be three or more vehicles ahead of you? (Round your answer to 1 decimal place.)27. Customers enter the waiting line to pay for food as they leave a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is two per minute and the average service rate of a single server is five per minute, what portion of the time is there less than 3 people in line? Answer to three decimal points please and thank you
- 1.) What does not decrease system utilization? increase in arrival rate increase in service rate increase in the number of servers decrease in the service time 2.) When a customer is waiting in line and decides to leave a system, this is known as anti-queuing reneging jockeying hesitatingPaula Caplin is manager of a major electronics repair facilityowned by Fisher Electronics. Recently, top management ex-pressed concern over the growth in the number of repair jobs in process at the facility. The average arrival rate is 120 jobsper day. The average job spends four days at the facility.a. What is the current work-in-process level at the facility?b. Suppose that top management has put a limit of one-halfthe current level of work-in-process. What goal mustPaula establish, and how might she accomplish it?At a border inspection station, vehicles arrive at the rate of 10 per hour in a Poisson distribution. For simplicity in this problem, assume that there is only one lane and one inspector, who can inspect vehicles at the rate of 15 per hour in an exponentially distributed fashion. a. What is the average length of the waiting line? (Round your answer to 2 decimal places.) b. What is the average total time it takes for a vehicle to get through the system? (Round your answer to 2 decimal places.) c. What is the utilization of the inspector? (Round your answer to 1 decimal place.) d. What is the probability that when you arrive there will be three or more vehicles ahead of you? (Round your answer to 1 decimal place.)
- 28. Customers enter the waiting line to pay for food as they leave a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is two per minute and the average service rate of a single server is five per minute, what is the average number of customers in line? Answer to three decimal points. thanks!A vending machine dispenses hot chocolate or coffee. Service time is 30 seconds per cup and is constant. Customers arrive at a mean rate of 76 per hour, and this rate is Poisson-distributed. a. Determine the average number of customers waiting in line. (Round your answer to 2 decimal places.) Average number of customer b. Determine the average time customers spend in the system. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Average time minutes c. Determine the average number of customers in the system. (Do not round intermediate calculations. Round your answer to 2 decimal places.) Average number customers92 Benny the Barber owns a one-chair shop. At barber college, they told Benny that his customers would exhibit a Poisson arrival distribution and that he would provide an exponential service distribution. His market survey data indicate that customers arrive at a rate of 2.5 per hour. It will take Benny an average of 20 minutes to give a haircut. Based on these figures, find the following: a. The average number of customers waiting Note: Round your intermediate calculations to 3 decimal places and final answer to 2 decimal places. b. The average time a customer waits. Note: Round your answer to 2 decimal places. c. The average time a customer is in the shop. Note: Round your intermediate calculations to 3 decimal places and final answer to 1 decimal place.