ACTIVITY PREDECESSORS DURATION (DAYS) A 3 B A 4 A D B 5 1 F D,E F,G 4 3 You are required to a) Draw the network diagram b) Calculate ES, EF, LS, LT c) Calculate slack time d) Identify critical path and activities
Q: A project for improving a billing process has the following precedence relationships and activity…
A:
Q: 2) Draw the network corresponding to the following information. Also, complete the table, identify…
A: Critical Path : B----D----G----H Critical Path Duration : 30
Q: A. Construct a network for the project outlined below and determine the critical path time B.…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: A network consists of the activities in the following list. Times are given in weeks. Activity…
A: ESActivityEFLSTimeLFES=maximum (EF of all immediate predecessor)EF=ES+durationLF=minimum (LS of all…
Q: SESSION 2– Individual exercise (for marks) Given the following activity precedence table, please…
A: The question is related to Critical Path Analysis. The details are given.
Q: a. Draw a project network. b. Identify the critical path. e Develop the activity schedule for the…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: The activity details and their predecessors are given below along with their activity times.…
A: The construction of the network is very important to understand the flow of activities in the…
Q: The following information is available about a project to organize an event to honor the mayor of…
A: a.
Q: Draw the project PDM. b. Determine the critical path. c. Calculate the total slack time. а.
A: In this question, I would first determine the expected activity time for each activity, based on the…
Q: REQUIRED: 1. Draw an Activity-on-Node network diagram for the project 2. Compute the Early Start…
A:
Q: activities, define the located activities on the critical path, define the total project duration,…
A: Find the Given details below: Activity Precedent Activity Time (Week) A - 7 B - 5 C B, E…
Q: a) Create an activity network diagram that shows the sequential logic the project tasks. b) Identify…
A: The critical path method (CPM) is a method for determining schedule flexibility and identifying…
Q: A project network is shown below. Use a forward and a backward pass to determine the critical path,…
A:
Q: please answer ASAP Table 1 Activity Immediate Predecessor Time (day) ES EF LS LF A - 2…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Activity (day) Predecessor(s) A 6…
A: Given data is
Q: 1. Activity Preceding activity Activity duration A - 6 B - 3 C B 1 D A, C 2 E…
A: Given Information:
Q: The following information concerns a project to raise moneyfor the Kids Against Crime…
A:
Q: 6. A Project network is shown below. Use forward and backward pass to determine th critical path and…
A: PERT is very useful techniques which are common among organizations to reduce cost and to represent…
Q: Given the activities whose sequence is described by thefol lowing table, draw the appropriate…
A: Critical path refers to the stage sequences, that require maximum time for the project completion.
Q: QI/ The following table shows the activities of a construction project, sequences and estimated…
A:
Q: a)Construct AON diagram for the following data. b) Identify path, path duration and critical path c)…
A: Below is the solution:-
Q: QI: Draw the arrow diagram for the following activities and show the critical path: activity…
A: ES -Early start time LS - Late start time EF - Early finish time LF - Late finish time ES = maximum…
Q: Q2. A. According to the following table which represents a project :(CLO Activity Predecessor…
A: Activity on Arrow (AoA) Action on Arrow (AoA) is a network diagraming strategy that explains the…
Q: Example - Draw Activity on Node Diagram Activity Predecessor Duration A B A 3 B E F G C,F 5 H G 4 G…
A: Activity Immediate Predecessors Duration A - 5 B A 3 C B 4 D - 5 E D 7 F E 2 G C,F 5…
Q: oger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: The project network is the diagrammatic form in which project activities and their durations are…
Q: Construct a CPM network based on activity on node method with the details given below and find the…
A: Given information, Activity Immediate Predecessor Duration A 1 B A 4 C A 2 D A 2 E…
Q: (a) Construct a project network. (b) Determine the expected times and variances for each activity.…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each…
A: The project network is the visual representation of the project activities and their durations to…
Q: Activity Predecessor Time(weeks) A 8 B A 6 4 D E A 11 F B 3 D, E, F 1 Using Table A, what is the…
A: Network Diagram,
Q: (a). Draw the Activity on Node (AoN) network diagram. (b). Find the critical path and write that…
A: Below is the solution:-
Q: Activity Activity Activity Slack Predecessor Duration (In weeks) a 3 b 2 a d b,c 1 e 3 f d,e g d, f…
A:
Q: REQUIRED: a. Calculate t,(expected time) for each activity. For each activity, the estimates are to,…
A: Answer is as below
Q: REQUIRED: a. Prepare the PERT Network for the US Tea project b. What is the critical path and its…
A: The answer is as below:
Q: a. Draw a precedence diagram using AOA , AON and Gantt chart. b. Find the critical path using CPM.…
A: Below is the solution:-
Q: Task time estimates for a production line setup project at XYZ Company are as follows; Activity Time…
A: We are authorized to answer three subparts at a time since you have not mentioned which part you are…
Q: 1. A project has been defined to contain the following list of activities along with their required…
A: Note: You have posted multiple questions with multiple subparts, we can solve only one question per…
Q: 03 Proceed to solve the following problem by Critical Path Method. Name of Activity A Immediate…
A: Critical Path Method (CPM) is a task plan demonstrating strategy. Mr. Morgan R. Walker and James E.…
Q: 1. Time taken by different activities are as follows. Activity Immediate predecessor Time (Days) 10…
A: a) AON Network b) Critical Path Paths Total Duration Start-C-F-G-End 5+6+8 =19…
Q: Given the activities whose sequence is describedby the following table, draw the appropriate…
A: Draw the path
Q: Activity Preceding Activity Estimate in Months Start D Start 4 A Start 6. F D, A 7 E D G F, E 5 B F…
A: Given Information:
Q: Predecessors C, F 9. Activity A B. H, I None (Start) B, J D D. C. H. G\ Construct a CPM network for…
A: Edge Node1 → Node2 D 1→2 C 2→3 F 2→4 d 3→4 G 3→6 H 3→7 A 4→5 J 5→8 I 6→7 B 7→8…
Q: Immediate Activity Predecessor Time (days) 8 в 20 33 18 D E 20 F B B.C 10 H D EF G, H, I 4 (End) a)…
A: A network diagram is a visual representation of a project which helps to identify the project…
Q: Questions 1. Organize the information above in an activity precedence table showing the activity,…
A: Answer of all pats are below:-
Q: A D A A B,C D H D,E F H,G You are required to a) Draw the network diagram b) Calculate ES, EF, LS,…
A: The answer is as below:
Q: Activity Immediate Normal Time Cost/day Lower Time Predecessor (days) & Limit None 450 None 300 A 3…
A: Given data is
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: To complete the problem the following is necessary. 1) project network diagram (AON), 2) table that…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Draw a project network given the information below. Time (Days) Predecessor Description First…
A: A network diagram is the pictorial representation of all the activities in the project in…
Pert And CPM Analaysis
Step by step
Solved in 3 steps with 1 images
- Question 1After collecting all those information, David is trying to conceptualize his problem. Supposeyou were David, how you will analysing the problem.You are expected to describe and investigate the problem in a more systematic way, andprovide answers for:• What were the key decisions?• What were the key uncertainties?• What was the timing of decisions?• What was the timing of the resolution of uncertainty?• What data would he need in order to make an intelligent, defensible decision?ul T-Mobile ? 22:07 89 % A coffeyvillecommunitycollege.mrooms.net Question 7 Not complete Marked out of 2.00 P Flag question In Norway and Sweden, there are: Select one: a. more bisexual relationships than same sex male relationships b. more male same sex registered partnerships than female same sex partnerships c. more bisexual relationships than same sex female relationships d. more female same sex registered partnerships than male same sex partnerships Check Question 8 Not complete Marked out of 2.00 P Flag questionQuestion Completion Status: Year 1 2 seconds. Tucson Macninary, Inc. manufacturers numerically controlled macnines (NCMS), which sell for an average price of $0.5 million each. Sales for these NCMS for the past two years were as follows: P Quarter 1 Quarter 2 Quarter 3 Quarter 4 12 18 26 16 16 24 28 18 What season factor would be associated with the fourth quarter? Show the formula you used and how you derived the answer. For the toolbar, press ALT+F10 (PC) or ALT+FN+F10 (Mac). BIUS Paragraph Arial A Moving to another question will save this response. 10pt hyji 27 描く A Bb toggle_stat... A N IQ5 0 WORDS POWERED BY TINY Question 8 of 19 > >> 1:34 PM 9/30/2022
- Question 4 "You are a project manager for a 10,000 sf industrial garage project in Toronto with a contract value of $1,350,000 and a contract duration of 6 months. You are preparing a status report for the project at the end of Month 3. The following progress data is available. What would be the forecast for estimate at completion for the project as of this reporting period? Use the CPI method of forecasting." PROJECT PLANNED DURATION REPORTING PERIOD Project Progress Data Planned Value (PV) Earned Value (EV) Actual Cost (AC) O "$1,080,000" "$1,215,000" O "$1,323,000" O "$1,161,000" INDUSTRIAL BUILDING 6 MONTHS MONTH 3 Month 1 $225,000 $250,000 $225,000 Month 2 $225,000 $250,000 $225,000 Month 3 $225,000 $250,000 $225,000 Month 4 $225,000 Month 5 $225,000 Month 6 $225,000QUESTION 1 Sales of Fat Lips Burgers for 2012 are shown in the table below. 1. Do the 2 month SMA forecast 2. Do 2 month WMA forecast using the information below WMA – 2: last month, 1 – last 2 months 3. For the month of January 2012, the forecast was 438. Do the EMA forecast with the smoothing constant = 0.3. What is the forecast for Jan 2013? 4. Compare the forecasts above using MAD, MSE and MAPE. Which forecast method gives the least errors? Month Actual Sales Forecast Jan 2012 438 Feb 420 March 414 Apr 318 May 306 June 240 July 240 Aug 216 Sep 198 Oct 225 Nov 270 Dec 315 Jan 2013 - QUESTION 2Dayang sells 5 kg bags of fertilizer to local farmers in Tg Karang. The sales data for the past 11 months is shown below. Month Demand (10s of bags) 1 4 2 6 3 4 4 5 5 10 6 8 7 7 8 9 9 12 10 14 11 15 1. Find the forecast for the month 12 using the methods below: a. Simple 4 month moving average (SMA) b.…question 10. The forecast was 70 units for the current period while actual demand was 76. The forecast for the next period is 75.8. What's alpha if a simple exponential smoothing forecast methoc being used? 6 OA. 0.097 OB. 0.967 OC. 0.004 OD. 0.040 Mark for review (Will be highlighted on the review page) > LOST LO EAST DONT Review My Answers 18°C Mostly cloudy AENG CERTIFICATE OF TRAMMING TRANSPORTATION OF DANGEROUS GOODS CERTIFICATE DE FORMATION TRANSPORT DES MERCHANDS DANGEREUSES James Purkisarajah Klean or N Save & Exit 75 Advance Blvd Brampton, Onta 2:52 F 2022-18
- W AutoSave Off H PGDPM AA Calendar JULY 2022 Final No Label ✓ File Home Insert Draw Design Layout 2 U Undo Page 29 of 32 ■ Paste X CA Clipboard Arial Q Search BIU U 32 of 5102 words 12 References A A Aa A x² A ab x₂ D✓ Av ab Font Mailings 6 QUESTION THREE QUESTION FOUR Review Search English (South Africa) Text Predictions: On 17° View Help ← = = = 三 H↓¶ Paragraph POSTGRADUATE DIPLOMA IN PROJECT MANAGEMENT - ACADEMIC AND ASSESSMENT CALENDAR Normal No Spacing 3.1 List and discuss at least 5 critical success factors for project quality management 3.2 Provide a diagram that best represents the quality management process and explain why this process is important. List and provide an overview of the processes in Quality Management Styles Accessibility: Unavailable W END OF PROJECT QUALITY MANAGEMENT Heading 1 5 Thembi Mdepa TM Comments Editing Dictate Focus Voice Sensitivity Sensitivity A ENG US Editing Editor Reuse Files Editor Reuse Files Share 4) b V + 100% 14:01 2023/04/10QUESTION 8 The point in the supply chain where the business switches from forecast-driven to demand-driven is called the point.Question Three: Jane is trying to forecast demand for her store, using moving average with n=2, Fill in the missing cells with correct values and find average error for first quarter and second quarter of year 2000 A B D E F Enroll- Abs Error Year 1997 Quarter 1 Forecast Error ment 313 285 312 339 4. 3 4 1998 1 359 7 2 320 8 3 356 9. 4 385 10 1999 1 396 11 2 367 12 3 397 13 4 423 14 2000 1 15 2000 2 123 5
- Question 15 conside ther following payoff table Alternatives 1 2 probability None of the choices 170 30 A 100 200 10 100 states of nature How much should be paid for a perfect forecast of the state of nature? 0.4 B 150 100 0.6Research topic: The study of customers’ behavior towards online shopping as opposed to in-store at a Supermarket. The Problem: would there be a problem conducting such research topic? If so, what are the possible problems?QUESTION 1 The table below shows the sales figures for a brand of shoe over the last 12 months. Months SalesJanuary 69February 75March 86April 92May 95June 100July 108August 115September 125October 131November 140December 150 a. Using the following, forecast the sales for the months up to January the following year:-i. A simple three month moving average. ii. A three period weighted moving average using weights of 1, 2 and 3. Assign thehighest weight to the most recent data. iii. Exponential Smoothing when α= .6 and the forecast for March is 350.iv. Determine which of the three forecasting technique is the most accurate using MAD