A generating station has a maximum demand of 75MW and a yearly load factor of 45%. Annual Generating costs inclusive of station capital costs are 1200 Dinars/kW demand plus 80 Dinars/kWh transmitted. The annual capital charges for transmission system are 40 million Dinars and for distribution system 30 million Dinars ; the respective diversity factors being 1:3 and 1:4. The efficiency of transmission system is 90% and that of the distribution system inclusive of substation losses is 85%. Find the yearly cost per kW demand and cost per kWh supplied : (1) at the substation (2) at the consumers premises.

Power System Analysis and Design (MindTap Course List)
6th Edition
ISBN:9781305632134
Author:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Chapter2: Fundamentals
Section: Chapter Questions
Problem 2.11P
icon
Related questions
Question
A generating station has a maximum
demand of 75MW and a yearly load
factor of 45%. Annual Generating
costs inclusive of station capital
costs are 1200 Dinars/kW demand
plus 80 Dinars/kWh transmitted. The
annual capital charges for
transmission system are 40 million
Dinars and for distribution system 30
million Dinars ; the respective
diversity factors being 1:3 and 1-4. The
efficiency of transmission system is
90% and that of the distribution
system inclusive of substation losses
is 85%. Find the yearly cost per kW
demand and cost per kWh supplied :
(1) at the substation (2) at the
consumers premises.
Transcribed Image Text:A generating station has a maximum demand of 75MW and a yearly load factor of 45%. Annual Generating costs inclusive of station capital costs are 1200 Dinars/kW demand plus 80 Dinars/kWh transmitted. The annual capital charges for transmission system are 40 million Dinars and for distribution system 30 million Dinars ; the respective diversity factors being 1:3 and 1-4. The efficiency of transmission system is 90% and that of the distribution system inclusive of substation losses is 85%. Find the yearly cost per kW demand and cost per kWh supplied : (1) at the substation (2) at the consumers premises.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Stability Analysis in Power System
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, electrical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Power System Analysis and Design (MindTap Course …
Power System Analysis and Design (MindTap Course …
Electrical Engineering
ISBN:
9781305632134
Author:
J. Duncan Glover, Thomas Overbye, Mulukutla S. Sarma
Publisher:
Cengage Learning