Project Name
Construction of 200 capacity hostel f
Project Manager
Josephine Chinoro Ukom
Date 28-Jan-24
Version
WORK BREAKDOWN STRUCTURE TEMPLATE - TASKS Task No.
Task Description
1
Initiation Phase
1.1
Team Charter Deevelopment
1.2
Identify Stakeholders
1.3
Establish Project Team
1.3.1
Assign Project Roles and Responsibilities
1.4
Conduct Project Kickoff Meeting
2
Planning Phase
2.1
Define Project Scope
2.1.1
Identify Housing Needs for International Students
2.1.2
Determine Regulatory Standards
2.2
Develop Project Schedule
2.3
Create Project Budget
2.3.1
Estimate Funding Sources
2.3.2
Allocate Budget to Project Categories
2.4
Resource Planning
2.4.1
Identify Construction Material
2.4.2
Define Skilled Labor Requirments
2.4.3
Select Architectural and Engineering Services
2.5
Risk management
2.5.1
Identify Potential Risks
2.5.2
Develop Risk Mitigation Strategies
2.6
Communication Plan
2.6.1
Define Communication Methods
2.6.2
Establish Team Meeting Frequency
2.6.3
Determine Frequency of Status Reports
3
Execution Phase
3.1
Site Selection and Acquisition
3.1.1
Research Potential Sites
3.1.2
Obtain Necessary Approvals
3.2
Architectural and Engineering Design
3.2.1
Develop Building Plans
3.2.2
Ensure Compliance with Construction Codes
3.3
Construction
3.3.1
Commence Building Process
3.3.2
Monitor Progress and Quality Control
3.3.3
Implement Safety Precautions
3.4
Interior Furnishing
3.4.1
Select Furnishing Items
3.4.2
Oversee Interior Design and Space Planning
3.5
Regulatory Approval and Compliance
3.5.1
Obtain Necessary Regulatory Approvals
3.5.2
Ensure Compliance with Regulations
3.6
Collaboration with University
3.6.1
Engage with University Community
3.6.2
Establish Collaboration Agreement
3.7
Budget Management
3.7.1
Monitor Spending
3.7.2
Report Financial Situations
4
Control Phase
4.1
Amenities Setup
4.1.1
Set Up Hostel Amenities
4.2
Quality Control
4.2.1
Implement Ongoing Quality Checks
4.2.2
Ensure Compliance with Standards
4.3
Construction Completed
4.3.1
Finalize Building Process
4.3.3
Verify Completion Against Plans
5
Closing Phase
5.1
Project Review and Evaluation
5.1.1
Review Project Milestones
5.1.2
Evaluate Team Performance
5.2
Final Report
5.2.1
Document Achievements and Challenges
5.2.2
Verify Completion Against Plans
5.3
Project Closure Meeting
5.3.1
Communicate Project Closure
5.3.2
Recognize Team Contributions
for UCW student madu Task Owner
project manager
project manager
project manager
project manager
project manager
project manager
community outreach $communication manager
project manager
project manager
project Accountant
project Accountant
project Accountant
project manager
Construction Manager
Construction Manager
design and architectural lead
project manager
project manager
project manager
community outreach and communication manager
community outreach and communication manager
project manager
project manager
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Design/Architect lead
Construction Manager
Construction Manager
Design/ Architect Lead,Construction Manager
Construction Manager
Construction Manager
Construction Manager
project manager
project manager and coordinator
project manager
project manager
communication manager
project manager and quality assurance team
project manager
communication manager
project manager
Dependency
none
1.1
1.2
1.3
1.3.1
none
Project Scope
Housing Needs Identification
Regulatory standards and identification of housing needs.
Project Schedule
Project Budget
Estimate Funding Sources
project schedule
resource planning
resource planning
resource planning
all task
Manage Risk
identify potencial risk
all task
Communication Plan
communication plan
Communication Plan
3.1
3.1.1
3.1.2
3.2
3.2.1
3.2.2
3.3
3.3.1
3.3.2
3.3.3
3.4
3.4.1
3.4.2
3.5
3.5.1
3.5.2
3.6
3.6.1
3.6.2
3.7
3.7.1
3.4, 3.7
4.1
3.3
4.2
4.2.1
3.3
4.3
4.3
4.3
4.2
all task
5.1.1
4.3
4.3.3
5.2, 5.2.2
5.3
5.3.1